CPWD Analysis of Rates · Mortars

Mud mortar

Item number
3.18
Analysis basis
Detail of cost for one cum
Priced inputs
4
Derived rate
940.55 / one cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 3.18 Mud mortar — is derived from 4 priced inputs for one cum and works out to ₹940.55 per one cum after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0811Mud (dry)Materialcum1.08190.00205.20
0114BeldarLabourday0.63736.00463.68
0101BhistiLabourday0.315816.00257.04
9999SundriesMaterialL.S.6.452.2714.64
Cost of one cum
940.56
Say
940.55

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 148. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.