Cement mortar 1:2 (1 cement : 2 stone dust)
- Item number
- 3.12
- Analysis basis
- 1 cum
- Priced inputs
- 6
- Derived rate
- ₹5,252.00/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 3.12 (Cement mortar 1:2 (1 cement : 2 stone dust)) is derived from 6 priced inputs for 1 cum and works out to ₹5,252.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- (0.475 cum. of cement = 0.68 tonne) Cement required for cement mortar is 47.50%
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0367 | MAT | Portland CementPortland Cement (OPC-43 Grade) | tonne | 0.68 | 5,156.00 | 3,506.08 |
| 1159 | MAT | Stone dust | cum | 0.95 | 1,100.00 | 1,045.00 |
| 0114 | LAB | Beldar | day | 0.75 | 736.00 | 552.00 |
| 0101 | LAB | Bhisti | day | 0.07 | 816.00 | 57.12 |
| 9999 | MAT | Hire and running charges of mechanical mixer | L.S. | 26.91 | 2.27 | 61.09 |
| 9999 | MAT | Sundries | L.S. | 13.52 | 2.27 | 30.69 |
- Cost of 1.00 cum
- 5,251.98
- SAY
- ₹5,252.00
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 146
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 146. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.