CPWD Analysis of Rates · Mortars
Cement mortar 1:6 (1 cement : 6 coarse sand)
- Item number
- 3.11
- Analysis basis
- Details of cost for 1 cum
- Priced inputs
- 6
- Derived rate
- ₹3,541.40 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 3.11 — Cement mortar 1:6 (1 cement : 6 coarse sand) — is derived from 6 priced inputs for 1 cum and works out to ₹3,541.40 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- (0.178 cum. of cement = 0.25 tonne) Cement required for cement mortar is 17.80%
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0367 | Portland CementPortland Cement (OPC-43 Grade)Material | tonne | 0.25 | 5,156.00 | 1,289.00 |
| 0982 | Coarse sand (zone III)Material | cum | 1.07 | 1,450.00 | 1,551.50 |
| 0114 | BeldarLabour | day | 0.75 | 736.00 | 552.00 |
| 0101 | BhistiLabour | day | 0.07 | 816.00 | 57.12 |
| 9999 | Hire and running charges of mechanical mixerMaterial | L.S. | 26.91 | 2.27 | 61.09 |
| 9999 | SundriesMaterial | L.S. | 13.52 | 2.27 | 30.69 |
- Cost of 1.00 cum
- 3,541.40
- Say
- 3,541.40
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 146. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.