Skip to main content

CPWD Analysis of Rates · Masonry Work

Extra for brick work / AAC block masonry / Tile brick masonry in superstructure above floor V level, for each four floors or part thereof by mechanical means

Item number
6.5
Analysis basis
Details of cost for 5.3 cum per four floors .
Priced inputs
1
Derived rate
169.45 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.5 Extra for brick work / AAC block masonry / Tile brick masonry in superstructure above floor V level, for each four floors or part thereof by mechanical means — is derived from 1 priced inputs for 5.3 cum and works out to ₹169.45 per cum after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0037Mobile craneMachineryday0.1255,050.00631.25
TOTAL
631.25
Add 1 % Water charges on “W”
6.31
TOTAL
637.56
Add GST on “X” (multiplying factor 0.2127)
135.61
TOTAL
773.17
Add 15% CPOH on “Y”
115.98
TOTAL
889.15
Add Cess @ 1% on “Z”
8.89
Cost of 5.3 Cum.
898.04
Cost for 1 cum
169.44
Say
169.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 311. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works