CPWD Analysis of Rates · Masonry Work
Extra for brick work / AAC block masonry / Tile brick masonry in superstructure above floor V level, for each four floors or part thereof by mechanical means
- Item number
- 6.5
- Analysis basis
- Details of cost for 5.3 cum per four floors .
- Priced inputs
- 1
- Derived rate
- ₹169.45 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.5 — Extra for brick work / AAC block masonry / Tile brick masonry in superstructure above floor V level, for each four floors or part thereof by mechanical means — is derived from 1 priced inputs for 5.3 cum and works out to ₹169.45 per cum after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0037 | Mobile craneMachinery | day | 0.125 | 5,050.00 | 631.25 |
- TOTAL
- 631.25
- Add 1 % Water charges on “W”
- 6.31
- TOTAL
- 637.56
- Add GST on “X” (multiplying factor 0.2127)
- 135.61
- TOTAL
- 773.17
- Add 15% CPOH on “Y”
- 115.98
- TOTAL
- 889.15
- Add Cess @ 1% on “Z”
- 8.89
- Cost of 5.3 Cum.
- 898.04
- Cost for 1 cum
- 169.44
- Say
- 169.45
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 311. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.