Brick work with non modular fly ash bricks conforming to IS:12894, class designation 10 average compressive strength in super structure above plinth level up to floor V level in
- Item number
- 6.34.1
- Analysis basis
- 1 cum
- Priced inputs
- 9
- Derived rate
- ₹8,962.35/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.34.1 (Brick work with non modular fly ash bricks conforming to IS:12894, class designation 10 average compressive strength in super structure above plinth level up to floor V level in : Cement mortar 1:4 (1 cement : 4 coarse sand)) is derived from 9 priced inputs for 1 cum and works out to ₹8,962.35 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Cement mortar 1 : 4 (1 cement : 4 coarse
- sand)
- Extra labour element required for lifting of
- materials above floor two level upto floor
- V level (0.75 x 1.5 = 1.13)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7737 | MAT | Fly ash bricks conforming to I.S. 12894 | 1000 Nos | 0.487 | 4,500.00 | 2,191.50 |
| SUB | Rate as per Item Number 3.9 of SH: MortarsRate as per item 3.9 | cum | 0.22 | 4,211.70 | 926.57 | |
| 9999 | MAT | Sundries | L.S. | 2.73 | 2.27 | 6.20 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.47 | 897.00 | 421.59 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.47 | 816.00 | 383.52 |
| 0115 | LAB | Coolie | day | 1.8 | 736.00 | 1,324.80 |
| 0101 | LAB | Bhisti | day | 0.2 | 816.00 | 163.20 |
| 9999 | MAT | Scaffolding | L.S. | 22.36 | 2.27 | 50.76 |
| 0115 | LAB | Coolie | day | 1.13 | 736.00 | 831.68 |
- TOTAL
- 6,299.82
- Add 1 % Water charges on “W”
- +63.00
- TOTAL
- 6,362.82
- Add GST on “X” (multiplying factor 0.2127)
- +1,353.37
- TOTAL
- 7,716.19
- Add 15% CPOH on “Y”
- +1,157.43
- TOTAL
- 8,873.62
- Add Cess @ 1% on “Z”
- +88.74
- Cost per cum.
- 8,962.36
- SAY
- ₹8,962.35
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 333
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 333. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.