R/DAR 2023

Brick work with non modular fly ash bricks conforming to IS:12894, class designation 10 average compressive strength in super structure above plinth level up to floor V level in

Cement mortar 1:4 (1 cement : 4 coarse sand)
Item number
6.34.1
Analysis basis
1 cum
Priced inputs
9
Derived rate
₹8,962.35/ CUM
D-01/RATE ANALYSISITEM 6.34.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.34.1 (Brick work with non modular fly ash bricks conforming to IS:12894, class designation 10 average compressive strength in super structure above plinth level up to floor V level in : Cement mortar 1:4 (1 cement : 4 coarse sand)) is derived from 9 priced inputs for 1 cum and works out to ₹8,962.35 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement mortar 1 : 4 (1 cement : 4 coarse
  • sand)
  • Extra labour element required for lifting of
  • materials above floor two level upto floor
  • V level (0.75 x 1.5 = 1.13)
ANALYSIS OF RATES · ITEM 6.34.1DETAILS OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7737MATFly ash bricks conforming to I.S. 128941000 Nos0.4874,500.002,191.50
SUBRate as per Item Number 3.9 of SH: MortarsRate as per item 3.9cum0.224,211.70926.57
9999MATSundriesL.S.2.732.276.20
0123LABMason 1st classMason 1st classday0.47897.00421.59
0124LABMason 2nd classMason 2nd classday0.47816.00383.52
0115LABCoolieday1.8736.001,324.80
0101LABBhistiday0.2816.00163.20
9999MATScaffoldingL.S.22.362.2750.76
0115LABCoolieday1.13736.00831.68
BUILD-UP TO RATE
TOTAL
6,299.82
Add 1 % Water charges on “W”
+63.00
TOTAL
6,362.82
Add GST on “X” (multiplying factor 0.2127)
+1,353.37
TOTAL
7,716.19
Add 15% CPOH on “Y”
+1,157.43
TOTAL
8,873.62
Add Cess @ 1% on “Z”
+88.74
Cost per cum.
8,962.36
SAY
₹8,962.35
D-02/SOURCEPRINTED PAGE 333
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
333

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 333. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.