Brick work with common burnt clay machine moulded perforated modular bricks of class designation 12.5 conforming to IS : 2222 in exposed brick work including making horizontal and vertical grooves 10 mm wide 12mm deep complete in cement mortar 1:6 (1 cement : 6 coarse sand)

From ground level upto plinth level
Item number
6.31.1
Analysis basis
1 cum
Priced inputs
7
Derived rate
₹7,032.05/ CUM
D-01/RATE ANALYSISITEM 6.31.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.31.1 (Brick work with common burnt clay machine moulded perforated modular bricks of class designation 12.5 conforming to IS : 2222 in exposed brick work including making horizontal and vertical grooves 10 mm wide 12mm deep complete in cement mortar 1:6 (1 cement : 6 coarse sand) From ground level upto plinth level) is derived from 7 priced inputs for 1 cum and works out to ₹7,032.05 per cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 6.31.1DETAILS OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7902MATMachine moulded common burnt clay modular perforated bricks of class designation 12.51000 Nos0.4875,500.002,678.50
SUBCement mortar 1 : 6 (1 cement : 6 coarse sand) (Rate as per item No 3.11)Rate as per item 3.11cum0.223,541.40779.11
9999MATSundries i/c steel / wooden strips for making groovesL.S.16.382.2737.18
0123LABMason 1st classMason 1st classday0.33897.00296.01
0124LABMason 2nd classMason 2nd classday0.33816.00269.28
0115LABCoolieday1736.00736.00
0101LABBhistiday0.18816.00146.88
BUILD-UP TO RATE
TOTAL
4,942.96
Add 1 % Water charges on “W”
+49.43
TOTAL
4,992.39
Add GST on “X” (multiplying factor 0.2127)
+1,061.88
TOTAL
6,054.27
Add 15% CPOH on “Y”
+908.14
TOTAL
6,962.41
Add Cess @ 1% on “Z”
+69.62
Cost of 1 Cum.
7,032.03
SAY
₹7,032.05
D-02/SOURCEPRINTED PAGE 331
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
331

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 331. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSMASONRY WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.