Brick work with common burnt clay machine moulded perforated modular bricks of class designation 12.5 conforming to IS : 2222 in exposed brick work including making horizontal and vertical grooves 10 mm wide 12mm deep complete in cement mortar 1:6 (1 cement : 6 coarse sand)
- Item number
- 6.31.1
- Analysis basis
- 1 cum
- Priced inputs
- 7
- Derived rate
- ₹7,032.05/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.31.1 (Brick work with common burnt clay machine moulded perforated modular bricks of class designation 12.5 conforming to IS : 2222 in exposed brick work including making horizontal and vertical grooves 10 mm wide 12mm deep complete in cement mortar 1:6 (1 cement : 6 coarse sand) From ground level upto plinth level) is derived from 7 priced inputs for 1 cum and works out to ₹7,032.05 per cum after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7902 | MAT | Machine moulded common burnt clay modular perforated bricks of class designation 12.5 | 1000 Nos | 0.487 | 5,500.00 | 2,678.50 |
| SUB | Cement mortar 1 : 6 (1 cement : 6 coarse sand) (Rate as per item No 3.11)Rate as per item 3.11 | cum | 0.22 | 3,541.40 | 779.11 | |
| 9999 | MAT | Sundries i/c steel / wooden strips for making grooves | L.S. | 16.38 | 2.27 | 37.18 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.33 | 897.00 | 296.01 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.33 | 816.00 | 269.28 |
| 0115 | LAB | Coolie | day | 1 | 736.00 | 736.00 |
| 0101 | LAB | Bhisti | day | 0.18 | 816.00 | 146.88 |
- TOTAL
- 4,942.96
- Add 1 % Water charges on “W”
- +49.43
- TOTAL
- 4,992.39
- Add GST on “X” (multiplying factor 0.2127)
- +1,061.88
- TOTAL
- 6,054.27
- Add 15% CPOH on “Y”
- +908.14
- TOTAL
- 6,962.41
- Add Cess @ 1% on “Z”
- +69.62
- Cost of 1 Cum.
- 7,032.03
- SAY
- ₹7,032.05
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 331
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 331. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.