Brick work with common burnt clay machine moulded perforated F.P.S. (non modular) bricks of class designation 12.5 conforming IS : 2222 in exposed brick work including making horizontal and vertical grooves 10mm wide 12 mm deep complete in cement mortar 1:6 (1 cement : 6 coarse sand)

Above plinth level upto floor V level
Item number
6.30.2
Analysis basis
1 cum
Priced inputs
9
Derived rate
₹9,344.00/ CUM
D-01/RATE ANALYSISITEM 6.30.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.30.2 (Brick work with common burnt clay machine moulded perforated F.P.S. (non modular) bricks of class designation 12.5 conforming IS : 2222 in exposed brick work including making horizontal and vertical grooves 10mm wide 12 mm deep complete in cement mortar 1:6 (1 cement : 6 coarse sand) Above plinth level upto floor V level) is derived from 9 priced inputs for 1 cum and works out to ₹9,344.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Extra labour for lifting of material (above
  • floor two level up to floor five level)
ANALYSIS OF RATES · ITEM 6.30.2DETAILS OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7901MATMachine moulded perforated common burnt clay FPS (non modular) bricks of class designation 12.51000 Nos0.4945,000.002,470.00
SUBRate as per Item Number 3.11 of SH: MortarsRate as per item 3.11cum0.253,541.40885.35
9999MATSundries i/c steel / wooden strips for making groovesL.S.16.382.2737.18
0123LABMason 1st classMason 1st classday0.47897.00421.59
0124LABMason 2nd classMason 2nd classday0.47816.00383.52
0115LABCoolieday1.8736.001,324.80
0101LABBhistiday0.2816.00163.20
0115LABCoolieday1.13736.00831.68
9999MATSundriesL.S.22.362.2750.76
BUILD-UP TO RATE
TOTAL
6,568.08
Add 1 % Water charges on “W”
+65.68
TOTAL
6,633.76
Add GST on “X” (multiplying factor 0.2127)
+1,411.00
TOTAL
8,044.76
Add 15% CPOH on “Y”
+1,206.71
TOTAL
9,251.47
Add Cess @ 1% on “Z”
+92.51
Cost of 1 Cum.
9,343.98
SAY
₹9,344.00
D-02/SOURCEPRINTED PAGE 330
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
330

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 330. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.