CPWD Analysis of Rates · Masonry Work
Brick work with common burnt clay machine moulded F.P.S. (non modular) bricks of class designation 12.5 in exposed brick work including making horizontal and vertical grooves 10 mm wide 12 mm deep complete in cement mortar 1:6 (1 cement : 6 coarse sand)
From ground level upto plinth level
- Item number
- 6.29.1
- Analysis basis
- Details of cost for 1 cum.
- Priced inputs
- 7
- Derived rate
- ₹7,581.15 / Cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.29.1 — Brick work with common burnt clay machine moulded F.P.S. (non modular) bricks of class designation 12.5 in exposed brick work including making horizontal and vertical grooves 10 mm wide 12 mm deep complete in cement mortar 1:6 (1 cement : 6 coarse sand) From ground level upto plinth level — is derived from 7 priced inputs for 1 cum and works out to ₹7,581.15 per cum after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7903 | Machine moulded common burnt clay FPS (non modular) bricks of class designation 12.5Material | 1000 Nos | 0.494 | 5,300.00 | 2,618.20 |
| Rate as per Item Number 3.11 of SH: MortarsRate as per item 3.11Sub-analysis | cum | 0.25 | 3,541.40 | 885.35 | |
| 9999 | Sundries i/c steel / wooden strips for making groovesMaterial | L.S. | 16.38 | 2.27 | 37.18 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.36 | 897.00 | 322.92 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.36 | 816.00 | 293.76 |
| 0115 | CoolieLabour | day | 1.37 | 736.00 | 1,008.32 |
| 0101 | BhistiLabour | day | 0.2 | 816.00 | 163.20 |
- TOTAL
- 5,328.93
- Add 1 % Water charges on “W”
- 53.29
- TOTAL
- 5,382.22
- Add GST on “X” (multiplying factor 0.2127)
- 1,144.80
- TOTAL
- 6,527.02
- Add 15% CPOH on “Y”
- 979.05
- TOTAL
- 7,506.07
- Add Cess @ 1% on “Z”
- 75.06
- Cost of 1 Cum.
- 7,581.13
- Say
- 7,581.15
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 328. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.