CPWD Analysis of Rates · Masonry Work

Brick work with common burnt clay machine moulded modular bricks of class designation 12.5 in exposed brick work including making horizontal and vertical grooves 10 mm wide 12 mm deep complete in cement mortar 1:6 (1 cement : 6 coarse sand)

Above plinth level upto floor V level

Item number
6.28.2
Analysis basis
Details of cost for 1 cum.
Priced inputs
9
Derived rate
8,971.10 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.28.2 Brick work with common burnt clay machine moulded modular bricks of class designation 12.5 in exposed brick work including making horizontal and vertical grooves 10 mm wide 12 mm deep complete in cement mortar 1:6 (1 cement : 6 coarse sand) Above plinth level upto floor V level — is derived from 9 priced inputs for 1 cum and works out to ₹8,971.10 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Extra labour for lifting of material (above
  • floor two level up to floor five level)
CodeInputUnitQuantityRate (INR)Amount (INR)
1986Common burnt clay modular bricks class designation 12.5Material1000 Nos0.4875,450.002,654.15
Rate as per Item Number 3.11 of SH: MortarsRate as per item 3.11Sub-analysiscum0.223,541.40779.11
9999Sundries including steel/wooden strips for making groovesMaterialL.S.16.382.2737.18
0123Mason 1st classMason 1st classLabourday0.44897.00394.68
0124Mason 2nd classMason 2nd classLabourday0.44816.00359.04
0115CoolieLabourday1.43736.001,052.48
0101BhistiLabourday0.18816.00146.88
0115CoolieLabourday1.13736.00831.68
9999SundriesMaterialL.S.22.362.2750.76
TOTAL
6,305.96
Add 1 % Water charges on “W”
63.06
TOTAL
6,369.02
Add GST on “X” (multiplying factor 0.2127)
1,354.69
TOTAL
7,723.71
Add 15% CPOH on “Y”
1,158.56
TOTAL
8,882.27
Add Cess @ 1% on “Z”
88.82
Cost per cum.
8,971.09
Say
8,971.10

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 328. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.