Brick work with common burnt clay modular bricks of class designation 7.5 in foundation and plinth in
- Item number
- 6.2.2
- Analysis basis
- 1 cum
- Priced inputs
- 7
- Derived rate
- ₹6,295.15/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.2.2 (Brick work with common burnt clay modular bricks of class designation 7.5 in foundation and plinth in: Cement Mortar 1:6 (1 cement : 6 coarse sand)) is derived from 7 priced inputs for 1 cum and works out to ₹6,295.15 per cum after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7900 | MAT | Modular common burnt clay bricks of class designation 7.5 | 1000 Nos | 0.487 | 4,500.00 | 2,191.50 |
| SUB | Rate as per item No 3.11 of SH: MortarRate as per item 3.11 | cum | 0.22 | 3,541.40 | 779.11 | |
| 9999 | MAT | Sundries | L.S. | 2.73 | 2.27 | 6.20 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.33 | 897.00 | 296.01 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.33 | 816.00 | 269.28 |
| 0115 | LAB | Coolie | day | 1 | 736.00 | 736.00 |
| 0101 | LAB | Bhisti | day | 0.18 | 816.00 | 146.88 |
- TOTAL
- 4,424.98
- Add 1 % Water charges on “W”
- +44.25
- TOTAL
- 4,469.23
- Add GST on “X” (multiplying factor 0.2127)
- +950.61
- TOTAL
- 5,419.84
- Add 15% CPOH on “Y”
- +812.98
- TOTAL
- 6,232.82
- Add Cess @ 1% on “Z”
- +62.33
- Cost of 1 Cum.
- 6,295.15
- SAY
- ₹6,295.15
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 308
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 308. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.