Brick work with common burnt clay modular bricks of class designation 7.5 in foundation and plinth in

Cement mortar 1:4 (1 cement : 4 coarse sand)
Item number
6.2.1
Analysis basis
1 cum
Priced inputs
7
Derived rate
₹6,504.90/ CUM
D-01/RATE ANALYSISITEM 6.2.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.2.1 (Brick work with common burnt clay modular bricks of class designation 7.5 in foundation and plinth in: Cement mortar 1:4 (1 cement : 4 coarse sand)) is derived from 7 priced inputs for 1 cum and works out to ₹6,504.90 per cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 6.2.1DETAILS OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7900MATModular common burnt clay bricks of class designation 7.51000 Nos0.4874,500.002,191.50
SUBRate as per item No 3.9 of SH: MortarRate as per item 3.9cum0.224,211.70926.57
9999MATSundriesL.S.2.732.276.20
0123LABMason 1st classMason 1st classday0.33897.00296.01
0124LABMason 2nd classMason 2nd classday0.33816.00269.28
0115LABCoolieday1736.00736.00
0101LABBhistiday0.18816.00146.88
BUILD-UP TO RATE
TOTAL
4,572.44
Add 1 % Water charges on “W”
+45.72
TOTAL
4,618.16
Add GST on “X” (multiplying factor 0.2127)
+982.28
TOTAL
5,600.44
Add 15% CPOH on “Y”
+840.07
TOTAL
6,440.51
Add Cess @ 1% on “Z”
+64.41
Cost of 1 Cum.
6,504.92
SAY
₹6,504.90
D-02/SOURCEPRINTED PAGE 308
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
308

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 308. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSMASONRY WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.