Tile brick masonry with common burnt clay machine moulded tile bricks of class designation 12.5 conforming to IS : 2690 (Part I) in foundation and plinth in cement mortar 1:6 (1 cement : 6 coarse sand)
- Item number
- 6.17
- Analysis basis
- 1 cum
- Priced inputs
- 7
- Derived rate
- ₹11,328.50/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.17 (Tile brick masonry with common burnt clay machine moulded tile bricks of class designation 12.5 conforming to IS : 2690 (Part I) in foundation and plinth in cement mortar 1:6 (1 cement : 6 coarse sand)) is derived from 7 priced inputs for 1 cum and works out to ₹11,328.50 per cum after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7904 | MAT | Machine moulded common burnt clay tile bricks of class designation 12.5 | 1000 Nos | 0.777 | 5,200.00 | 4,040.40 |
| SUB | Rate as per Item Number 3.11 of SH: MortarsRate as per item 3.11 | cum | 0.4 | 3,541.40 | 1,416.56 | |
| 9999 | MAT | Sundries | L.S. | 4.55 | 2.27 | 10.33 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.7 | 897.00 | 627.90 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.7 | 816.00 | 571.20 |
| 0115 | LAB | Coolie | day | 1.54 | 736.00 | 1,133.44 |
| 0101 | LAB | Bhisti | day | 0.2 | 816.00 | 163.20 |
- TOTAL
- 7,963.03
- Add 1 % Water charges on “W”
- +79.63
- TOTAL
- 8,042.66
- Add GST on “X” (multiplying factor 0.2127)
- +1,710.67
- TOTAL
- 9,753.33
- Add 15% CPOH on “Y”
- +1,463.00
- TOTAL
- 11,216.33
- Add Cess @ 1% on “Z”
- +112.16
- Cost of 1 Cum.
- 11,328.49
- SAY
- ₹11,328.50
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 320
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 320. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.