CPWD Analysis of Rates · Masonry Work
Extra for providing and placing in position 2 Nos 6mm dia. M.S. bars at every third course of half brick masonry
- Item number
- 6.15
- Analysis basis
- Details of cost for 100sqm.
- Priced inputs
- 2
- Derived rate
- ₹104.80
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.15 — Extra for providing and placing in position 2 Nos 6mm dia. M.S. bars at every third course of half brick masonry — is derived from 2 priced inputs and works out to ₹104.80 after water charges, GST, CPOH and cess. The full build-up is below.
- 6mm dia. M.S. bars (round) 2 Nos. @ 30
- meter/10sqm. = 10x60 metre @ 0.22kg/m
- = 132 kg
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1002 | Mild steel round bar 6 mm diaMild steel round bar 12 mm dia and belowMaterial | quintal | 1.32 | 5,550.00 | 7,326.00 |
| 9999 | SundriesMaterial | L.S. | 18.2 | 2.27 | 41.31 |
- TOTAL
- 7,367.31
- Add 1 % Water charges on “W”
- 73.67
- TOTAL
- 7,440.98
- Add GST on “X” (multiplying factor 0.2127)
- 1,582.70
- TOTAL
- 9,023.68
- Add 15% CPOH on “Y”
- 1,353.55
- TOTAL
- 10,377.23
- Add Cess @ 1% on “Z”
- 103.77
- Cost for 100 sqm.
- 10,481.00
- Cost for 1 sqm.
- 104.81
- Say
- 104.80
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 319. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works