Skip to main content
R/DAR 2023

Extra for half brick masonry in superstructure, above floor V level for every four floors or part thereof by mechanical means

Item number
6.14
Analysis basis
59.83 sqm
Priced inputs
1
Derived rate
₹15.00/ SQM
D-01/RATE ANALYSISITEM 6.14

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.14 (Extra for half brick masonry in superstructure, above floor V level for every four floors or part thereof by mechanical means) is derived from 1 priced inputs for 59.83 sqm and works out to ₹15.00 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • floors .
ANALYSIS OF RATES · ITEM 6.14DETAILS OF COST FOR 59.83 SQM PER FOUR
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0037MACHMobile craneday0.1255,050.00631.25
BUILD-UP TO RATE
TOTAL
631.25
Add 1 % Water charges on “W”
+6.31
TOTAL
637.56
Add GST on “X” (multiplying factor 0.2127)
+135.61
TOTAL
773.17
Add 15% CPOH on “Y”
+115.98
TOTAL
889.15
Add Cess @ 1% on “Z”
+8.89
Cost of 59.83 sqm.
898.04
Cost for 1 sqm
15.01
SAY
₹15.00
D-02/SOURCEPRINTED PAGE 318
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
318

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 318. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSMASONRY WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.