CPWD Analysis of Rates · Masonry Work
Extra for half brick masonry in superstructure, above floor V level for every four floors or part thereof by mechanical means
- Item number
- 6.14
- Analysis basis
- Details of cost for 59.83 sqm per four
- Priced inputs
- 1
- Derived rate
- ₹15.00 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.14 — Extra for half brick masonry in superstructure, above floor V level for every four floors or part thereof by mechanical means — is derived from 1 priced inputs for 59.83 sqm and works out to ₹15.00 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- floors .
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0037 | Mobile craneMachinery | day | 0.125 | 5,050.00 | 631.25 |
- TOTAL
- 631.25
- Add 1 % Water charges on “W”
- 6.31
- TOTAL
- 637.56
- Add GST on “X” (multiplying factor 0.2127)
- 135.61
- TOTAL
- 773.17
- Add 15% CPOH on “Y”
- 115.98
- TOTAL
- 889.15
- Add Cess @ 1% on “Z”
- 8.89
- Cost of 59.83 sqm.
- 898.04
- Cost for 1 sqm
- 15.01
- Say
- 15.00
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 318. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works