CPWD Analysis of Rates · Flooring
Providing and fixing removable raised/false access flooring with system and its components of approved make for different plenum height with possible height adjustment upto 50 mm, comprising of modular load bearing floor panels supported on G.I. rectangular stinger frame work and G.I. Pedestal etc. all complete, as per the architectural drawings, as specified and as directed by Engineer-in-charge consisting of: (a) Providing at required spacing to form modular framework, pedestals made out of GI tube of thickness minimum 2 mm and 25 mm outer diameter, fully welded on to the G.I. Base plate of size 100mm x 100mm x 3mm at the bottom of the pedestal tube, G.I. pedestal head of size 75mmx75mmx3.5 mm welded with GI fully threaded stud 16mm outer diameter with two GI Check nuts screwed on the stud for level adjustment upto 50mm, locking and stabilizing the pedestal head in position at the required level. The pedestals shall be fixed to the subfloor (base) through base plate using epoxy based adhesive of approved make or the machine screw with rawl plug. (b) Stringers system in all steel construction hot dipped galvanized of rectangular size 570x20x30x0.80mm thick having holes at both ends for securing the stringers on to the pedestal head using fully threaded screws ensuring maximum lateral stability in all directions, the grid formed by the pedestal and stringer assembly shall receive the floor panel, this system shall provide adequate solid, rigid support for access floor panel, the system shall provide a minimum clear uninterrupted clearance between the bottom of the floor for electrical conduits and wiring etc. all complete as per the architectural drawings, as specified and as directed by the Engineer-in-charge. (c) Providing and fixing Access Floor panel of 600x600x32 mm medium grade Filled Steel anti static high pressure Lamination of 800H grade (FS800H). Access Floor panel shall be steel welded construction with an enclosed bottom pan with uniform pattern of 64 hemispherical cones. The top and bottom plates of Steel Gauges: top 0.6 mm and bottom 0.7 mm fused spot welded together (minimum 64 welds in each dome and 20 welds along each flange). The panel should be Corroresist epoxy coated for lifetime rust protection and cavity formed by the top and bottom plate is filled with Pyrogrip noncombustible Portland cementitious core mixed with lightweight foaming compound. The access floor shall be factory finished with Anti-static High Pressure laminate with Non Warp technology upto 1mm thickness for superior adhesion and Surface flatness within 0.75mm.The panel is to withstand a Concentrated Load of 363 kgs applied on area 25mm x 25mm without collapse in the centre of the panel which is placed on four steel blocks. The panel will withstand and Uniformly Distributed Load (UDL) minimum 1250 kg/sqm and an impact load of 50kg all complete as per the approved manufacturers specification and as per the direction of Engineer-in-charge. All specification must be printed on the side of the panel to ensure the quality of the product
300 mm Finished Floor Height (FFH)
- Item number
- 11.54.1
- Analysis basis
- Details of Cost for : 100.00 Sqm
- Priced inputs
- 9
- Derived rate
- ₹5,623.95 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.54.1 — Providing and fixing removable raised/false access flooring with system and its components of approved make for different plenum height with possible height adjustment upto 50 mm, comprising of modular load bearing floor panels supported on G.I. rectangular stinger frame work and G.I. Pedestal etc. all complete, as per the architectural drawings, as specified and as directed by Engineer-in-charge consisting of: (a) Providing at required spacing to form modular framework, pedestals made out of GI tube of thickness minimum 2 mm and 25 mm outer diameter, fully welded on to the G.I. Base plate of size 100mm x 100mm x 3mm at the bottom of the pedestal tube, G.I. pedestal head of size 75mmx75mmx3.5 mm welded with GI fully threaded stud 16mm outer diameter with two GI Check nuts screwed on the stud for level adjustment upto 50mm, locking and stabilizing the pedestal head in position at the required level. The pedestals shall be fixed to the subfloor (base) through base plate using epoxy based adhesive of approved make or the machine screw with rawl plug. (b) Stringers system in all steel construction hot dipped galvanized of rectangular size 570x20x30x0.80mm thick having holes at both ends for securing the stringers on to the pedestal head using fully threaded screws ensuring maximum lateral stability in all directions, the grid formed by the pedestal and stringer assembly shall receive the floor panel, this system shall provide adequate solid, rigid support for access floor panel, the system shall provide a minimum clear uninterrupted clearance between the bottom of the floor for electrical conduits and wiring etc. all complete as per the architectural drawings, as specified and as directed by the Engineer-in-charge. (c) Providing and fixing Access Floor panel of 600x600x32 mm medium grade Filled Steel anti static high pressure Lamination of 800H grade (FS800H). Access Floor panel shall be steel welded construction with an enclosed bottom pan with uniform pattern of 64 hemispherical cones. The top and bottom plates of Steel Gauges: top 0.6 mm and bottom 0.7 mm fused spot welded together (minimum 64 welds in each dome and 20 welds along each flange). The panel should be Corroresist epoxy coated for lifetime rust protection and cavity formed by the top and bottom plate is filled with Pyrogrip noncombustible Portland cementitious core mixed with lightweight foaming compound. The access floor shall be factory finished with Anti-static High Pressure laminate with Non Warp technology upto 1mm thickness for superior adhesion and Surface flatness within 0.75mm.The panel is to withstand a Concentrated Load of 363 kgs applied on area 25mm x 25mm without collapse in the centre of the panel which is placed on four steel blocks. The panel will withstand and Uniformly Distributed Load (UDL) minimum 1250 kg/sqm and an impact load of 50kg all complete as per the approved manufacturers specification and as per the direction of Engineer-in-charge. All specification must be printed on the side of the panel to ensure the quality of the product 300 mm Finished Floor Height (FFH) — is derived from 9 priced inputs and works out to ₹5,623.95 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- MATERIALS :
- LABOUR :
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 2711 | FS800H Grade Flooring Panel (i/c) 5% wastageFS800H Grade Flooring Panel (Size 600 mm x600 mm x32 mm)Material | each | 292 | 748.00 | 2,18,416.00 |
| 2712 | Zinc Electroplated Pedestals - 300 mmMaterial | each | 360 | 147.00 | 52,920.00 |
| 2714 | Zinc Electroplated Tube StingerMaterial | each | 570 | 74.00 | 42,180.00 |
| 2715 | Machine Screw for FixingMaterial | each | 1,140 | 4.00 | 4,560.00 |
| 7048 | Rawl Plug fl0or pedestal grouting on floorRawl plug 50 mm (designation 10)Material | each | 1,440 | 24.00 | 34,560.00 |
| 9999 | Carriage of materialMaterial | L.S. | 490 | 2.27 | 1,112.30 |
| 0111 | Carpenter 1st classLabour | day | 25 | 897.00 | 22,425.00 |
| 0114 | BeldarLabour | day | 25 | 736.00 | 18,400.00 |
| 9999 | SundriesMaterial | L.S. | 329 | 2.27 | 746.83 |
- TOTAL
- 3,95,320.13
- Add 1 % Water charges on “W”
- 3,953.20
- TOTAL
- 3,99,273.33
- Add GST on “X” (multiplying factor 0.2127)
- 84,925.44
- TOTAL
- 4,84,198.77
- Add 15% CPOH on “Y”
- 72,629.82
- TOTAL
- 5,56,828.59
- Add Cess @ 1% on “Z”
- 5,568.29
- Cost of 100 sqm.
- 5,62,396.88
- Cost of 1 sqm
- 5,623.97
- Say
- 5,623.95
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 844. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.