CPWD Analysis of Rates · Flooring

Providing and fixing Glass mossaic tiles on finished plain wall surface of size 20 mm x 20 mm x 4 mm in all colour, design , fixing in customize design as per direction of EngineerinCharge. The glass mosaic tiles to be fixed on the wall surface with the help of approved adhesive applied at the rate of 2.5 kg per sqm and grouting of the same. The rate is inclusive of all operation, material and required pattern approved by Engineer-in-Charge:

Item number
11.53
Analysis basis
Details of cost per 8 sqm
Priced inputs
8
Derived rate
3,891.15

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.53 Providing and fixing Glass mossaic tiles on finished plain wall surface of size 20 mm x 20 mm x 4 mm in all colour, design , fixing in customize design as per direction of EngineerinCharge. The glass mosaic tiles to be fixed on the wall surface with the help of approved adhesive applied at the rate of 2.5 kg per sqm and grouting of the same. The rate is inclusive of all operation, material and required pattern approved by Engineer-in-Charge: — is derived from 8 priced inputs and works out to ₹3,891.15 after water charges, GST, CPOH and cess. The full build-up is below.

  • Glass mossaic tiles (20 mm x 20 mm x
  • 4mm)
  • LABOUR :
  • (for finishing , polishing and fixing)
  • Add for wastage 2.5%= 0.2 sqm
  • Total: 8.20 sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
1242Glass mossaic tiles (20 mm x 20 mm x 4 mm)Materialsqm8.22,270.0018,614.00
1243Tile fixing chemical adhesiveMaterialkg2012.00240.00
1244Cement Polymer Grout CompoundMaterialkg1016.00160.00
1245Acid for cleaning tilesMateriallitre420.0080.00
9999carriage of marble slabMaterialL.S.49.922.27113.32
0123Mason 1st classMason 1st classLabourday1.6897.001,435.20
0115CoolieLabourday1.6736.001,177.60
9999Sundries including carriage of adhesive etcMaterialL.S.26.912.2761.09
TOTAL
21,881.21
Add 1 % Water charges on “W”
218.81
TOTAL
22,100.02
Add GST on “X” (multiplying factor 0.2127)
4,700.67
TOTAL
26,800.69
Add 15% CPOH on “Y”
4,020.10
TOTAL
30,820.79
Add Cess @ 1% on “Z”
308.21
Cost for 8.00 sqm
31,129.00
Cost for 1.00 sqm
3,891.13
Say
3,891.15

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 843. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.