Providing and fixing Glass mossaic tiles on finished plain wall surface of size 20 mm x 20 mm x 4 mm in all colour, design , fixing in customize design as per direction of EngineerinCharge. The glass mosaic tiles to be fixed on the wall surface with the help of approved adhesive applied at the rate of 2.5 kg per sqm and grouting of the same. The rate is inclusive of all operation, material and required pattern approved by Engineer-in-Charge:

Item number
11.53
Analysis basis
Details of cost per 8 sqm
Priced inputs
8
Derived rate
₹3,891.15
D-01/RATE ANALYSISITEM 11.53

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.53 (Providing and fixing Glass mossaic tiles on finished plain wall surface of size 20 mm x 20 mm x 4 mm in all colour, design , fixing in customize design as per direction of EngineerinCharge. The glass mosaic tiles to be fixed on the wall surface with the help of approved adhesive applied at the rate of 2.5 kg per sqm and grouting of the same. The rate is inclusive of all operation, material and required pattern approved by Engineer-in-Charge:) is derived from 8 priced inputs and works out to ₹3,891.15 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Glass mossaic tiles (20 mm x 20 mm x
  • 4mm)
  • LABOUR :
  • (for finishing , polishing and fixing)
  • Add for wastage 2.5%= 0.2 sqm
  • Total: 8.20 sqm
ANALYSIS OF RATES · ITEM 11.53DETAILS OF COST PER 8 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1242MATGlass mossaic tiles (20 mm x 20 mm x 4 mm)sqm8.22,270.0018,614.00
1243MATTile fixing chemical adhesivekg2012.00240.00
1244MATCement Polymer Grout Compoundkg1016.00160.00
1245MATAcid for cleaning tileslitre420.0080.00
9999MATcarriage of marble slabL.S.49.922.27113.32
0123LABMason 1st classMason 1st classday1.6897.001,435.20
0115LABCoolieday1.6736.001,177.60
9999MATSundries including carriage of adhesive etcL.S.26.912.2761.09
BUILD-UP TO RATE
TOTAL
21,881.21
Add 1 % Water charges on “W”
+218.81
TOTAL
22,100.02
Add GST on “X” (multiplying factor 0.2127)
+4,700.67
TOTAL
26,800.69
Add 15% CPOH on “Y”
+4,020.10
TOTAL
30,820.79
Add Cess @ 1% on “Z”
+308.21
Cost for 8.00 sqm
31,129.00
Cost for 1.00 sqm
3,891.13
SAY
₹3,891.15
D-02/SOURCEPRINTED PAGE 843
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
843

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 843. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFLOORING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.