CPWD Analysis of Rates · Flooring
Providing and fixing Glass mossaic tiles on finished plain wall surface of size 20 mm x 20 mm x 4 mm in all colour, design , fixing in customize design as per direction of EngineerinCharge. The glass mosaic tiles to be fixed on the wall surface with the help of approved adhesive applied at the rate of 2.5 kg per sqm and grouting of the same. The rate is inclusive of all operation, material and required pattern approved by Engineer-in-Charge:
- Item number
- 11.53
- Analysis basis
- Details of cost per 8 sqm
- Priced inputs
- 8
- Derived rate
- ₹3,891.15
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.53 — Providing and fixing Glass mossaic tiles on finished plain wall surface of size 20 mm x 20 mm x 4 mm in all colour, design , fixing in customize design as per direction of EngineerinCharge. The glass mosaic tiles to be fixed on the wall surface with the help of approved adhesive applied at the rate of 2.5 kg per sqm and grouting of the same. The rate is inclusive of all operation, material and required pattern approved by Engineer-in-Charge: — is derived from 8 priced inputs and works out to ₹3,891.15 after water charges, GST, CPOH and cess. The full build-up is below.
- Glass mossaic tiles (20 mm x 20 mm x
- 4mm)
- LABOUR :
- (for finishing , polishing and fixing)
- Add for wastage 2.5%= 0.2 sqm
- Total: 8.20 sqm
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1242 | Glass mossaic tiles (20 mm x 20 mm x 4 mm)Material | sqm | 8.2 | 2,270.00 | 18,614.00 |
| 1243 | Tile fixing chemical adhesiveMaterial | kg | 20 | 12.00 | 240.00 |
| 1244 | Cement Polymer Grout CompoundMaterial | kg | 10 | 16.00 | 160.00 |
| 1245 | Acid for cleaning tilesMaterial | litre | 4 | 20.00 | 80.00 |
| 9999 | carriage of marble slabMaterial | L.S. | 49.92 | 2.27 | 113.32 |
| 0123 | Mason 1st classMason 1st classLabour | day | 1.6 | 897.00 | 1,435.20 |
| 0115 | CoolieLabour | day | 1.6 | 736.00 | 1,177.60 |
| 9999 | Sundries including carriage of adhesive etcMaterial | L.S. | 26.91 | 2.27 | 61.09 |
- TOTAL
- 21,881.21
- Add 1 % Water charges on “W”
- 218.81
- TOTAL
- 22,100.02
- Add GST on “X” (multiplying factor 0.2127)
- 4,700.67
- TOTAL
- 26,800.69
- Add 15% CPOH on “Y”
- 4,020.10
- TOTAL
- 30,820.79
- Add Cess @ 1% on “Z”
- 308.21
- Cost for 8.00 sqm
- 31,129.00
- Cost for 1.00 sqm
- 3,891.13
- Say
- 3,891.15
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 843. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works