Providing and fixing glazed screen printed border tile 75mm wide having thickness 5mm, of approved quality & make, in all shades, design and prints, in dado, over 12mm thick bed of cement mortar 1:3 (1 Cement : 3 Coarse sand) and jointing with grey cement slurry @ 3.3 kg/sqm including pointing with white cement mixed with pigment of matching shade, all complete as approved by Engineer - in - Charge

Item number
11.46A
Analysis basis
Details of cost for 133.33 metre
Priced inputs
8
Derived rate
216.20 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.46A Providing and fixing glazed screen printed border tile 75mm wide having thickness 5mm, of approved quality & make, in all shades, design and prints, in dado, over 12mm thick bed of cement mortar 1:3 (1 Cement : 3 Coarse sand) and jointing with grey cement slurry @ 3.3 kg/sqm including pointing with white cement mixed with pigment of matching shade, all complete as approved by Engineer - in - Charge — is derived from 8 priced inputs for 133.33 metre and works out to ₹216.20 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • Details for 10 sqm (i.e.
  • 10.00/0.075=133.33m length)
  • Tile required=10.00/(0.20x0.075)=666.67
  • tile.
  • Total= 683.34 say 683 tiles
  • Add 2.5% wastage = 16.67 tile
CodeInputUnitQuantityRate (INR)Amount (INR)
8624Border tiles 200x75mm size 5mm thickBorder tiles 200x75 mm sizeMaterialeach68320.0013,660.00
9999CarriageMaterialL.S.62.42.27141.65
Cement mortar 1:3 for 12mm baseRate as per item 3.8Sub-analysiscum0.144,881.95683.47
9999Mortar for pointing in white cementMaterialL.S.404.32.27917.76
0367Cement for slurry over bed @ 3.3kg/sqmPortland Cement (OPC-43 Grade)Materialtonne0.0335,156.00170.15
0123Mason 1st classMason 1st classLaboureach2.5897.002,242.50
0115CoolieLaboureach2.5736.001,840.00
9999Sundries 10x(26.91-0.16)=267.5MaterialL.S.267.52.27607.23
TOTAL
20,262.76
Add 1 % Water charges on “W”
202.63
TOTAL
20,465.39
Add GST on “X” (multiplying factor 0.2127)
4,352.99
TOTAL
24,818.38
Add 15% CPOH on “Y”
3,722.76
TOTAL
28,541.14
Add Cess @ 1% on “Z”
285.41
Cost per metre
216.20
Say
216.20

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 832. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works