Skip to main content

CPWD Analysis of Rates · Flooring

Providing and laying Vitrified tiles in different sizes (thickness to be specified by manufacturer), with water absorption less than 0.08 % and conforming to I.S. 15622, of approved make, in all colours & shade, in skirting, riser of steps, over 12 mm thick bed of cement mortar 1:3 (1 cement: 3 coarse sand), jointing with grey cement slurry @ 3.3 kg/ sqm including grouting the joint with white cement & matching pigments etc. complete

Size of Tile 1000x1000 mm

Item number
11.46.4
Analysis basis
Detail of cost for 10 sqm
Priced inputs
8
Derived rate
2,162.60 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.46.4 Providing and laying Vitrified tiles in different sizes (thickness to be specified by manufacturer), with water absorption less than 0.08 % and conforming to I.S. 15622, of approved make, in all colours & shade, in skirting, riser of steps, over 12 mm thick bed of cement mortar 1:3 (1 cement: 3 coarse sand), jointing with grey cement slurry @ 3.3 kg/ sqm including grouting the joint with white cement & matching pigments etc. complete Size of Tile 1000x1000 mm — is derived from 8 priced inputs for 10 sqm and works out to ₹2,162.60 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Vitrified floor tiles 100 x 100 cm size = 10
  • sqm+
  • sqm
  • Total = 10.25 sqm
  • 12 mm thick Cement mortar 1 : 3 (1
  • cement : 3 coarse sand)
  • Cement slurry over bed @ 3.3 kg per
  • sqm
  • Add wastage & breakage @ 2.5% = 0.25
CodeInputUnitQuantityRate (INR)Amount (INR)
8623Vitrified floor tile 100x100 cmVitrified floor tile 100x100 cm conforming to IS 15622:2006 group (B1a)Materialsqm10.25920.009,430.00
9977Carriage of tilesMaterialL.S.62.42.27141.65
Rate as per Item No.3.8 of SH:MORTARSRate as per item 3.8Sub-analysiscum0.144,881.95683.47
9999Mortar for pointing in white cementMaterialL.S.36.42.2782.63
0367Portland CementPortland Cement (OPC-43 Grade)Materialtonne0.0335,156.00170.15
0123Mason 1st classMason 1st classLabourday2.5897.002,242.50
0115CoolieLabourday2.5736.001,840.00
9988Sundries including carriage of quick set polymer etcMaterialL.S.269.12.27610.86
TOTAL
15,201.26
Add 1 % Water charges on “W”
152.01
TOTAL
15,353.27
Add GST on “X” (multiplying factor 0.2127)
3,265.64
TOTAL
18,618.91
Add 15% CPOH on “Y”
2,792.84
TOTAL
21,411.75
Add Cess @ 1% on “Z”
214.12
Cost of 10 sqm
21,625.87
Cost for 1 sqm
2,162.59
Say
2,162.60

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 831. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works