CPWD Analysis of Rates · Flooring

Size of Tile 800 x 800 mm

Item number
11.41A.1.2
Analysis basis
Detail of cost for 10 sqm
Priced inputs
9
Derived rate
1,534.85 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.41A.1.2 Size of Tile 800 x 800 mm — is derived from 9 priced inputs for 10 sqm and works out to ₹1,534.85 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Double Charged vitrified floor tiles 80
  • x 80 cm size =10 sqm+ Add wastage
  • & breakage @2.5% =0.25 sqm. Total =
  • 10.25 sqm
  • 20 mm thick Cement mortar 1 : 4 (1
  • cement : 4 coarse sand)
  • Cement for slurry over bed @ 3.3 kg per
  • sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
2753Double charge vitrified tile polished finish of size 80 x 80 cmMaterialsqm10.25534.005,473.50
9977Carriage of tilesMaterialL.S.62.42.27141.65
Rate as per Item Number 3.9 of SH: MortarsRate as per item 3.9Sub-analysiscum0.244,211.701,010.81
9999Mortar for pointing in white cementMaterialL.S.262.2759.02
0367Portland cementPortland Cement (OPC-43 Grade)Materialtonne0.0335,156.00170.15
9999For notch trowel,plier, wedge, clips of required thickness, leveling system and rubber mallet etcMaterialL.S.252.2756.75
0123Mason 1st classMason 1st classLabourday2897.001,794.00
0115CoolieLabourday2736.001,472.00
9988sundries including carriage of quick set polymer etcMaterialL.S.269.12.27610.86
TOTAL
10,788.74
Add 1% Water charges on “W”
107.89
TOTAL
10,896.63
Add GST on “X” (multiplying factor 0.2127)
2,317.71
TOTAL
13,214.34
Add 15% CPOH on “Y”
1,982.15
TOTAL
15,196.49
Add Cess @ 1% on “Z”
151.96
Cost of 10sqm
15,348.45
Cost of 1sqm
1,534.85
Say
1,534.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 815. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.