Providing and laying vitrified floor tiles in different sizes (thickness to be specified by the manufacturer) with water absorption less than 0.08% and conforming to IS: 15622, of approved make, in all colours and shades, laid on 20mm thick cement mortar 1:4 (1 cement : 4 coarse sand), jointing with grey cement slurry @ 3.3 kg/ sqm including grouting the joints with white cement and matching pigments etc., complete

Size of Tile 1000x1000 mm
Item number
11.41.4
Analysis basis
10 sqm
Priced inputs
8
Derived rate
₹2,089.65/ SQM
D-01/RATE ANALYSISITEM 11.41.4

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.41.4 (Providing and laying vitrified floor tiles in different sizes (thickness to be specified by the manufacturer) with water absorption less than 0.08% and conforming to IS: 15622, of approved make, in all colours and shades, laid on 20mm thick cement mortar 1:4 (1 cement : 4 coarse sand), jointing with grey cement slurry @ 3.3 kg/ sqm including grouting the joints with white cement and matching pigments etc., complete Size of Tile 1000x1000 mm) is derived from 8 priced inputs for 10 sqm and works out to ₹2,089.65 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Vitrified floor tiles 80x80 cm size = 10sqm
  • 0.25 sqm
  • Total = 10.25 sqm
  • 20 mm thick Cement mortar 1 : 4 (1
  • cement : 4 coarse sand)
  • Cement for slurry over bed @ 3.3 kg per
  • sqm
  • Add for wastage & breakage @ 2.5 % =
ANALYSIS OF RATES · ITEM 11.41.4DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8623MATVitrified floor tile 100x100 cmVitrified floor tile 100x100 cm conforming to IS 15622:2006 group (B1a)sqm10.25920.009,430.00
9977MATCarriage of tilesL.S.62.42.27141.65
SUBRate as per Item Number 3.9 of SH: MortarsRate as per item 3.9cum0.244,211.701,010.81
9999MATMortar for pointing in white cementL.S.262.2759.02
0367MATPortland CementPortland Cement (OPC-43 Grade)tonne0.0335,156.00170.15
0123LABMason 1st classMason 1st classday2897.001,794.00
0115LABCoolieday2736.001,472.00
9988MATSundries including carriage of cement etcL.S.269.12.27610.86
BUILD-UP TO RATE
TOTAL
14,688.49
Add 1 % Water charges on “W”
+146.88
TOTAL
14,835.37
Add GST on “X” (multiplying factor 0.2127)
+3,155.48
TOTAL
17,990.85
Add 15% CPOH on “Y”
+2,698.63
TOTAL
20,689.48
Add Cess @ 1% on “Z”
+206.89
Cost for 10 sqm
20,896.37
Cost for 1 sqm
2,089.64
SAY
₹2,089.65
D-02/SOURCEPRINTED PAGE 814
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
814

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 814. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.