Skip to main content
R/DAR 2023

Providing and laying vitrified floor tiles in different sizes (thickness to be specified by the manufacturer) with water absorption less than 0.08% and conforming to IS: 15622, of approved make, in all colours and shades, laid on 20mm thick cement mortar 1:4 (1 cement : 4 coarse sand), jointing with grey cement slurry @ 3.3 kg/ sqm including grouting the joints with white cement and matching pigments etc., complete

Size of Tile 800x800 mm
Item number
11.41.3
Analysis basis
10 sqm
Priced inputs
8
Derived rate
₹1,885.50/ SQM
D-01/RATE ANALYSISITEM 11.41.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.41.3 (Providing and laying vitrified floor tiles in different sizes (thickness to be specified by the manufacturer) with water absorption less than 0.08% and conforming to IS: 15622, of approved make, in all colours and shades, laid on 20mm thick cement mortar 1:4 (1 cement : 4 coarse sand), jointing with grey cement slurry @ 3.3 kg/ sqm including grouting the joints with white cement and matching pigments etc., complete Size of Tile 800x800 mm) is derived from 8 priced inputs for 10 sqm and works out to ₹1,885.50 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Vitrified floor tiles 80x80 cm size = 10sqm
  • 0.25 sqm
  • Total = 10.25 sqm
  • 20 mm thick Cement mortar 1 : 4 (1
  • cement : 4 coarse sand)
  • Cement for slurry over bed @ 3.3 kg per
  • sqm
  • Add for wastage & breakage @ 2.5 % =
ANALYSIS OF RATES · ITEM 11.41.3DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8622MATVitrified floor tile 80x80 cmVitrified floor tile 80x80 cm conforming to IS 15622:2006 group (B1a)sqm10.25780.007,995.00
9977MATCarriage of tilesL.S.62.42.27141.65
SUBRate as per Item Number 3.9 of SH: MortarsRate as per item 3.9cum0.244,211.701,010.81
9999MATMortar for pointing in white cementL.S.262.2759.02
0367MATPortland CementPortland Cement (OPC-43 Grade)tonne0.0335,156.00170.15
0123LABMason 1st classMason 1st classday2897.001,794.00
0115LABCoolieday2736.001,472.00
9988MATSundries including carriage of cement etcL.S.269.12.27610.86
BUILD-UP TO RATE
TOTAL
13,253.49
Add 1 % Water charges on “W”
+132.53
TOTAL
13,386.02
Add GST on “X” (multiplying factor 0.2127)
+2,847.21
TOTAL
16,233.23
Add 15% CPOH on “Y”
+2,434.98
TOTAL
18,668.21
Add Cess @ 1% on “Z”
+186.68
Cost for 10 sqm
18,854.89
Cost for 1 sqm
1,885.49
SAY
₹1,885.50
D-02/SOURCEPRINTED PAGE 813
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
813

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 813. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFLOORING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.