CPWD Analysis of Rates · Flooring
Providing and laying vitrified floor tiles in different sizes (thickness to be specified by the manufacturer) with water absorption less than 0.08% and conforming to IS: 15622, of approved make, in all colours and shades, laid on 20mm thick cement mortar 1:4 (1 cement : 4 coarse sand), jointing with grey cement slurry @ 3.3 kg/ sqm including grouting the joints with white cement and matching pigments etc., complete
Size of Tile 800x800 mm
- Item number
- 11.41.3
- Analysis basis
- Details of cost for 10 sqm
- Priced inputs
- 8
- Derived rate
- ₹1,885.50 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.41.3 — Providing and laying vitrified floor tiles in different sizes (thickness to be specified by the manufacturer) with water absorption less than 0.08% and conforming to IS: 15622, of approved make, in all colours and shades, laid on 20mm thick cement mortar 1:4 (1 cement : 4 coarse sand), jointing with grey cement slurry @ 3.3 kg/ sqm including grouting the joints with white cement and matching pigments etc., complete Size of Tile 800x800 mm — is derived from 8 priced inputs for 10 sqm and works out to ₹1,885.50 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Vitrified floor tiles 80x80 cm size = 10sqm
- 0.25 sqm
- Total = 10.25 sqm
- 20 mm thick Cement mortar 1 : 4 (1
- cement : 4 coarse sand)
- Cement for slurry over bed @ 3.3 kg per
- sqm
- Add for wastage & breakage @ 2.5 % =
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8622 | Vitrified floor tile 80x80 cmVitrified floor tile 80x80 cm conforming to IS 15622:2006 group (B1a)Material | sqm | 10.25 | 780.00 | 7,995.00 |
| 9977 | Carriage of tilesMaterial | L.S. | 62.4 | 2.27 | 141.65 |
| Rate as per Item Number 3.9 of SH: MortarsRate as per item 3.9Sub-analysis | cum | 0.24 | 4,211.70 | 1,010.81 | |
| 9999 | Mortar for pointing in white cementMaterial | L.S. | 26 | 2.27 | 59.02 |
| 0367 | Portland CementPortland Cement (OPC-43 Grade)Material | tonne | 0.033 | 5,156.00 | 170.15 |
| 0123 | Mason 1st classMason 1st classLabour | day | 2 | 897.00 | 1,794.00 |
| 0115 | CoolieLabour | day | 2 | 736.00 | 1,472.00 |
| 9988 | Sundries including carriage of cement etcMaterial | L.S. | 269.1 | 2.27 | 610.86 |
- TOTAL
- 13,253.49
- Add 1 % Water charges on “W”
- 132.53
- TOTAL
- 13,386.02
- Add GST on “X” (multiplying factor 0.2127)
- 2,847.21
- TOTAL
- 16,233.23
- Add 15% CPOH on “Y”
- 2,434.98
- TOTAL
- 18,668.21
- Add Cess @ 1% on “Z”
- 186.68
- Cost for 10 sqm
- 18,854.89
- Cost for 1 sqm
- 1,885.49
- Say
- 1,885.50
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 813. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.