40 mm thick rubbed stone flooring over 20 mm (average) thick base of cement mortar 1:5 (1 cement : 5 coarse sand) with joints 3 mm thick, side buttered with cement mortar 1:2 (1 cement : 2 stone dust) admixed with pigment to match the shade of stone and pointing with same mortar

Red sand stone
Item number
11.30.1
Analysis basis
Details of cost for 10sqm.
Priced inputs
11
Derived rate
₹1,647.00
D-01/RATE ANALYSISITEM 11.30.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.30.1 (40 mm thick rubbed stone flooring over 20 mm (average) thick base of cement mortar 1:5 (1 cement : 5 coarse sand) with joints 3 mm thick, side buttered with cement mortar 1:2 (1 cement : 2 stone dust) admixed with pigment to match the shade of stone and pointing with same mortar Red sand stone) is derived from 11 priced inputs and works out to ₹1,647.00 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Finished work = 10 sqm
  • Total = 11 sqm
  • Cement mortar 1 : 5 (1 cement : 5 coarse
  • sand)
  • (i) for beading = 0.224 cum+
  • (ii) for joining = 0.026 cum.
  • Total=0.250cum.
  • Cement mortar 1:2 (1 Cement : 2 stone
  • dust for pointing)
  • Labour for rubbing of stone
  • Add for wastage @ 10% = 1 sqm
ANALYSIS OF RATES · ITEM 11.30.1DETAILS OF COST FOR 10SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1164MATRed sand stone slab 40 mmthick (undressed)Red sand stone slab 40 mm thick (un-dressed)sqm11330.003,630.00
9977MATCarriageL.S.34.062.2777.32
SUBRate as per Item Number 3.10 of SH: MortarsRate as per item 3.10cum0.253,850.75962.69
SUBRate as per Item Number 3.12 of SH: MortarsRate as per item 3.12cum0.0235,252.00120.80
0123LABMason 1st classMason 1st classday3.9897.003,498.30
0100LABBandhaniday1.1816.00897.60
0115LABCoolieday1.4736.001,030.40
0101LABBhistiday0.55816.00448.80
9999MATSundriesL.S.26.912.2761.09
0139LABSkilled Beldar (for floor rubbing etc.)day0.618816.00504.29
0013MACHMachine for rubbing of floorsday0.988350.00345.80
BUILD-UP TO RATE
TOTAL
11,577.09
Add 1 % Water charges on “W”
+115.77
TOTAL
11,692.86
Add GST on “X” (multiplying factor 0.2127)
+2,487.07
TOTAL
14,179.93
Add 15% CPOH on “Y”
+2,126.99
TOTAL
16,306.92
Add Cess @ 1% on “Z”
+163.07
Cost for 10sqm.
16,469.99
Cost for 1sqm.
1,647.00
SAY
₹1,647.00
D-02/SOURCEPRINTED PAGE 803
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
803

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 803. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.