R/DAR 2023

Chequered terrazo tiles 22 mm thick with graded marble chips of size up to 6 mm in floors, jointed with neat cement slurry mixed with pigment to match the shade of the tiles, including rubbing and polishing complete, on 20 mm thick bed of cement mortar 1:4 (1 cement :4 coarse sand)

Light shade pigment using white cement
Item number
11.19.1
Analysis basis
10 sqm
Priced inputs
12
Derived rate
₹1,533.80/ SQM
D-01/RATE ANALYSISITEM 11.19.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.19.1 (Chequered terrazo tiles 22 mm thick with graded marble chips of size up to 6 mm in floors, jointed with neat cement slurry mixed with pigment to match the shade of the tiles, including rubbing and polishing complete, on 20 mm thick bed of cement mortar 1:4 (1 cement :4 coarse sand) : Light shade pigment using white cement) is derived from 12 priced inputs for 10 sqm and works out to ₹1,533.80 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement mortar 1 : 4 (1 cement :
  • 4 coarse sand)
  • Grey cement for slurry @ 4.4kg/sqm
  • White cement for grouting
ANALYSIS OF RATES · ITEM 11.19.1DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1227MATChequered terrazo tiles 22 mm thick (light shade) including 10% wastageChequered terrazzo tiles 22 mm thick (light shade)sqm11320.003,520.00
9977MATCarriage of tilesL.S.40.432.2791.78
SUBRate as per Item Number 3.9 of SH: MortarsRate as per item 3.9cum0.2244,211.70943.42
0367MATPortland CementPortland Cement (OPC-43 Grade)tonne0.0445,156.00226.86
0368MATWhite Cementtonne0.04410,500.00462.00
0875MATRed, chocolate, orange, buff or yellow (red oxide of iron) light shade pigmentRed, chocolate, orange, buff or yellow (red oxide of iron) light shade pigmentkilogram3.0865.00200.20
0124LABMason 2nd classMason 2nd classday1.6816.001,305.60
0115LABCoolieday2736.001,472.00
0139LABSkilled Beldar (for floor rubbing etc.)day1816.00816.00
0101LABBhistiday1816.00816.00
0013MACHMachine for rubbing of floorsday1.6350.00560.00
9999MATSundries including pigment wherever required and carborandum stone etcL.S.161.982.27367.69
BUILD-UP TO RATE
TOTAL
10,781.55
Add 1 % Water charges on “W”
+107.82
TOTAL
10,889.37
Add GST on “X” (multiplying factor 0.2127)
+2,316.17
TOTAL
13,205.54
Add 15% CPOH on “Y”
+1,980.83
TOTAL
15,186.37
Add Cess @ 1% on “Z”
+151.86
Cost of 10 sqm.
15,338.23
Cost of 1 sqm.
1,533.82
SAY
₹1,533.80
D-02/SOURCEPRINTED PAGE 784
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
784

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 784. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.