Chequered terrazo tiles 22 mm thick with graded marble chips of size up to 6 mm in floors, jointed with neat cement slurry mixed with pigment to match the shade of the tiles, including rubbing and polishing complete, on 20 mm thick bed of cement mortar 1:4 (1 cement :4 coarse sand)

Light shade pigment using white cement

Item number
11.19.1
Analysis basis
Details of cost for 10 sqm.
Priced inputs
12
Derived rate
1,533.80 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.19.1 Chequered terrazo tiles 22 mm thick with graded marble chips of size up to 6 mm in floors, jointed with neat cement slurry mixed with pigment to match the shade of the tiles, including rubbing and polishing complete, on 20 mm thick bed of cement mortar 1:4 (1 cement :4 coarse sand) : Light shade pigment using white cement — is derived from 12 priced inputs for 10 sqm and works out to ₹1,533.80 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Cement mortar 1 : 4 (1 cement :
  • 4 coarse sand)
  • Grey cement for slurry @ 4.4kg/sqm
  • White cement for grouting
CodeInputUnitQuantityRate (INR)Amount (INR)
1227Chequered terrazo tiles 22 mm thick (light shade) including 10% wastageChequered terrazzo tiles 22 mm thick (light shade)Materialsqm11320.003,520.00
9977Carriage of tilesMaterialL.S.40.432.2791.78
Rate as per Item Number 3.9 of SH: MortarsRate as per item 3.9Sub-analysiscum0.2244,211.70943.42
0367Portland CementPortland Cement (OPC-43 Grade)Materialtonne0.0445,156.00226.86
0368White CementMaterialtonne0.04410,500.00462.00
0875Red, chocolate, orange, buff or yellow (red oxide of iron) light shade pigmentRed, chocolate, orange, buff or yellow (red oxide of iron) light shade pigmentMaterialkilogram3.0865.00200.20
0124Mason 2nd classMason 2nd classLabourday1.6816.001,305.60
0115CoolieLabourday2736.001,472.00
0139Skilled Beldar (for floor rubbing etc.)Labourday1816.00816.00
0101BhistiLabourday1816.00816.00
0013Machine for rubbing of floorsMachineryday1.6350.00560.00
9999Sundries including pigment wherever required and carborandum stone etcMaterialL.S.161.982.27367.69
TOTAL
10,781.55
Add 1 % Water charges on “W”
107.82
TOTAL
10,889.37
Add GST on “X” (multiplying factor 0.2127)
2,316.17
TOTAL
13,205.54
Add 15% CPOH on “Y”
1,980.83
TOTAL
15,186.37
Add Cess @ 1% on “Z”
151.86
Cost of 10 sqm.
15,338.23
Cost of 1 sqm.
1,533.82
Say
1,533.80

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 784. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works