CPWD Analysis of Rates · Flooring

Precast terrazo tiles 22 mm thick with graded marble chips of sizes upto 12 mm, in skirting

Dark shade pigment using ordinary cement

Item number
11.18.3
Analysis basis
Details of cost for 10 sqm.
Priced inputs
9
Derived rate
2,308.75 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.18.3 Precast terrazo tiles 22 mm thick with graded marble chips of sizes upto 12 mm, in skirting Dark shade pigment using ordinary cement — is derived from 9 priced inputs for 10 sqm and works out to ₹2,308.75 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Cement mortar 1:3 (1 cement : 3 coarse
  • sand)
  • Grey cement for slurry
CodeInputUnitQuantityRate (INR)Amount (INR)
1203Precast terrazo tiles 22 mm thick (dark shade) including wastage & breakagePrecast terrazzo tiles 22 mm thick (dark shade)Materialsqm11285.003,135.00
9977Carriage of tilesMaterialL.S.40.432.2791.78
Rate as per Item Number 3.8 of SH: MortarsRate as per item 3.8Sub-analysiscum0.1444,881.95703.00
0367Portland CementPortland Cement (OPC-43 Grade)Materialtonne0.0665,156.00340.30
0874Black colour dark shade pigmentMaterialkilogram4.6275.00346.50
0124Mason 2nd classMason 2nd classLabourday3.25816.002,652.00
0115CoolieLabourday3.25736.002,392.00
0139Skilled Beldar (for floor rubbing etc.)Labourday7.6816.006,201.60
9999Sundries including pigment wherever required, carborandum stone and polishing powder etcMaterialL.S.161.462.27366.51
TOTAL
16,228.69
Add 1 % Water charges on “W”
162.29
TOTAL
16,390.98
Add GST on “X” (multiplying factor 0.2127)
3,486.36
TOTAL
19,877.34
Add 15% CPOH on “Y”
2,981.60
TOTAL
22,858.94
Add Cess @ 1% on “Z”
228.59
Cost of 10 sqm.
23,087.53
Cost of 1 sqm.
2,308.75
Say
2,308.75

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 782. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.