Precast terrazo tiles 22 mm thick with graded marble chips of sizes upto 12 mm, in skirting

and risers of steps not exceeding 30 cm in height, on 12 mm thick cement plaster 1:3 (1 cement : 3 coarse sand), jointed with neat cement slurry mixed with pigment to match the shade of the tiles, including rubbing and polishing complete with tiles of : Light shade pigment using white cement
Item number
11.18.1
Analysis basis
10 sqm
Priced inputs
9
Derived rate
₹2,422.80/ SQM
D-01/RATE ANALYSISITEM 11.18.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.18.1 (Precast terrazo tiles 22 mm thick with graded marble chips of sizes upto 12 mm, in skirting and risers of steps not exceeding 30 cm in height, on 12 mm thick cement plaster 1:3 (1 cement : 3 coarse sand), jointed with neat cement slurry mixed with pigment to match the shade of the tiles, including rubbing and polishing complete with tiles of : Light shade pigment using white cement) is derived from 9 priced inputs for 10 sqm and works out to ₹2,422.80 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement mortar 1:3 (1 cement : 3 coarse
  • sand)
  • For slurry
  • For buttering tiles bed sides =44 kg. +
  • For grouting =22 kg.
  • Total = 66 kg
  • 66x3.5/50 = 4.62
ANALYSIS OF RATES · ITEM 11.18.1DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1201MATPrecast terrazo tiles 22 mm thick (light shade) including 10% wastagePrecast terrazzo tiles 22 mm thick (light shade)sqm11330.003,630.00
9977MATCarriage of tilesL.S.40.432.2791.78
SUBRate as per Item Number 3.8 of SH: MortarsRate as per item 3.8cum0.1444,881.95703.00
0368MATWhite Cementtonne0.06610,500.00693.00
0875MATRed, chocolate, orange, buff or yellow (red oxide of iron) light shade pigmentRed, chocolate, orange, buff or yellow (red oxide of iron) light shade pigmentkilogram4.6265.00300.30
0124LABMason 2nd classMason 2nd classday3.25816.002,652.00
0115LABCoolieday3.25736.002,392.00
0139LABSkilled Beldar (for floor rubbing etc.)day7.6816.006,201.60
9999MATSundries including pigment wherever required, carborandum stone and polishing powder etcL.S.161.462.27366.51
BUILD-UP TO RATE
TOTAL
17,030.19
Add 1 % Water charges on “W”
+170.30
TOTAL
17,200.49
Add GST on “X” (multiplying factor 0.2127)
+3,658.54
TOTAL
20,859.03
Add 15% CPOH on “Y”
+3,128.85
TOTAL
23,987.88
Add Cess @ 1% on “Z”
+239.88
Cost of 10 sqm.
24,227.76
Cost of 1 sqm.
2,422.78
SAY
₹2,422.80
D-02/SOURCEPRINTED PAGE 781
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
781

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 781. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFLOORING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.