CPWD Analysis of Rates · Flooring

Precast terrazo tiles 22 mm thick with graded marble chips of sizes upto 12 mm, in skirting

and risers of steps not exceeding 30 cm in height, on 12 mm thick cement plaster 1:3 (1 cement : 3 coarse sand), jointed with neat cement slurry mixed with pigment to match the shade of the tiles, including rubbing and polishing complete with tiles of : Light shade pigment using white cement

Item number
11.18.1
Analysis basis
Details of cost for 10 sqm.
Priced inputs
9
Derived rate
2,422.80 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.18.1 Precast terrazo tiles 22 mm thick with graded marble chips of sizes upto 12 mm, in skirting and risers of steps not exceeding 30 cm in height, on 12 mm thick cement plaster 1:3 (1 cement : 3 coarse sand), jointed with neat cement slurry mixed with pigment to match the shade of the tiles, including rubbing and polishing complete with tiles of : Light shade pigment using white cement — is derived from 9 priced inputs for 10 sqm and works out to ₹2,422.80 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Cement mortar 1:3 (1 cement : 3 coarse
  • sand)
  • For slurry
  • For buttering tiles bed sides =44 kg. +
  • For grouting =22 kg.
  • Total = 66 kg
  • 66x3.5/50 = 4.62
CodeInputUnitQuantityRate (INR)Amount (INR)
1201Precast terrazo tiles 22 mm thick (light shade) including 10% wastagePrecast terrazzo tiles 22 mm thick (light shade)Materialsqm11330.003,630.00
9977Carriage of tilesMaterialL.S.40.432.2791.78
Rate as per Item Number 3.8 of SH: MortarsRate as per item 3.8Sub-analysiscum0.1444,881.95703.00
0368White CementMaterialtonne0.06610,500.00693.00
0875Red, chocolate, orange, buff or yellow (red oxide of iron) light shade pigmentRed, chocolate, orange, buff or yellow (red oxide of iron) light shade pigmentMaterialkilogram4.6265.00300.30
0124Mason 2nd classMason 2nd classLabourday3.25816.002,652.00
0115CoolieLabourday3.25736.002,392.00
0139Skilled Beldar (for floor rubbing etc.)Labourday7.6816.006,201.60
9999Sundries including pigment wherever required, carborandum stone and polishing powder etcMaterialL.S.161.462.27366.51
TOTAL
17,030.19
Add 1 % Water charges on “W”
170.30
TOTAL
17,200.49
Add GST on “X” (multiplying factor 0.2127)
3,658.54
TOTAL
20,859.03
Add 15% CPOH on “Y”
3,128.85
TOTAL
23,987.88
Add Cess @ 1% on “Z”
239.88
Cost of 10 sqm.
24,227.76
Cost of 1 sqm.
2,422.78
Say
2,422.80

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 781. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works