Extra if terrazo tiles are laid in treads of steps not exceeding 30 cm in width

Item number
11.17
Analysis basis
10 sqm
Priced inputs
3
Derived rate
₹124.05/ SQM
D-01/RATE ANALYSISITEM 11.17

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.17 (Extra if terrazo tiles are laid in treads of steps not exceeding 30 cm in width) is derived from 3 priced inputs for 10 sqm and works out to ₹124.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 11.17DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0124LABMason 2nd classMason 2nd classday0.22816.00179.52
0115LABCoolieday0.22736.00161.92
0139LABSkilled Beldar (for floor rubbing etc.)day0.65816.00530.40
BUILD-UP TO RATE
TOTAL
871.84
Add 1 % Water charges on “W”
+8.72
TOTAL
880.56
Add GST on “X” (multiplying factor 0.2127)
+187.30
TOTAL
1,067.86
Add 15% CPOH on “Y”
+160.18
TOTAL
1,228.04
Add Cess @ 1% on “Z”
+12.28
Cost of 10 sqm.
1,240.32
Cost of 1 sqm.
124.03
SAY
₹124.05
D-02/SOURCEPRINTED PAGE 780
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
780

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 780. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.