CPWD Analysis of Rates · Flooring
Precast terrazo tiles 22 mm thick with graded marble chips of size upto 12 mm, laid in floors, and landings, jointed with neat cement slurry mixed with pigment to match the shade of the tiles, including rubbing and polishing complete, on 20 mm thick bed of cement mortar 1:4 (1 cement:4 coarse sand)
Light shade pigment using white cement
- Item number
- 11.16.1
- Analysis basis
- Details of cost for 10 sqm.
- Priced inputs
- 12
- Derived rate
- ₹1,549.45 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.16.1 — Precast terrazo tiles 22 mm thick with graded marble chips of size upto 12 mm, laid in floors, and landings, jointed with neat cement slurry mixed with pigment to match the shade of the tiles, including rubbing and polishing complete, on 20 mm thick bed of cement mortar 1:4 (1 cement:4 coarse sand) : Light shade pigment using white cement — is derived from 12 priced inputs for 10 sqm and works out to ₹1,549.45 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Cement mortar 1 : 4 (1 cement : 4 coarse
- sand)
- Grey cement for slurry @ 4.4kg/sqm.
- for grouting
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1201 | Precast terrazo tiles 22 mm thick (light shade) including 10% wastagePrecast terrazzo tiles 22 mm thick (light shade)Material | sqm | 11 | 330.00 | 3,630.00 |
| 9977 | Carriage of tilesMaterial | L.S. | 40.43 | 2.27 | 91.78 |
| Rate as per Item Number 3.9 of SH: MortarsRate as per item 3.9Sub-analysis | cum | 0.224 | 4,211.70 | 943.42 | |
| 0367 | Portland CementPortland Cement (OPC-43 Grade)Material | tonne | 0.044 | 5,156.00 | 226.86 |
| 0368 | White CementMaterial | tonne | 0.044 | 10,500.00 | 462.00 |
| 0875 | Red, chocolate, orange, buff or yellow (red oxide of iron) light shade pigmentRed, chocolate, orange, buff or yellow (red oxide of iron) light shade pigmentMaterial | kilogram | 3.08 | 65.00 | 200.20 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 1.6 | 816.00 | 1,305.60 |
| 0115 | CoolieLabour | day | 2 | 736.00 | 1,472.00 |
| 0139 | Skilled Beldar (for floor rubbing etc.)Labour | day | 1 | 816.00 | 816.00 |
| 0101 | BhistiLabour | day | 1 | 816.00 | 816.00 |
| 0013 | Machine for rubbing of floorsMachinery | day | 1.6 | 350.00 | 560.00 |
| 9999 | Sundries including pigment wherever required and carborandum stone etcMaterial | L.S. | 161.98 | 2.27 | 367.69 |
- TOTAL
- 10,891.55
- Add 1 % Water charges on “W”
- 108.92
- TOTAL
- 11,000.47
- Add GST on “X” (multiplying factor 0.2127)
- 2,339.80
- TOTAL
- 13,340.27
- Add 15% CPOH on “Y”
- 2,001.04
- TOTAL
- 15,341.31
- Add Cess @ 1% on “Z”
- 153.41
- Cost of 10 sqm.
- 15,494.72
- Cost of 1 sqm.
- 1,549.47
- Say
- 1,549.45
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 777. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works