CPWD Analysis of Rates · Flooring
Crazy marble stone flooring, including filling the gaps with light shade pigment with white cement marble powder mixture (3 parts of white cement : 1 part of marble powder) by weight in proportion of 4:7 (4 cement marble powder mix : 7 white, black or white and black marble chips of sizes from 1 mm to 4 mm nominal size by volume), with under layer 25 mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 12.5 mm nominal size), including rubbing, polishing and cement slurry etc. complete
18 mm thick crazy marble stone white, black or as specified
- Item number
- 11.15.1
- Analysis basis
- Details of cost for 100 sqm.
- Priced inputs
- 16
- Derived rate
- ₹1,714.80 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.15.1 — Crazy marble stone flooring, including filling the gaps with light shade pigment with white cement marble powder mixture (3 parts of white cement : 1 part of marble powder) by weight in proportion of 4:7 (4 cement marble powder mix : 7 white, black or white and black marble chips of sizes from 1 mm to 4 mm nominal size by volume), with under layer 25 mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 12.5 mm nominal size), including rubbing, polishing and cement slurry etc. complete : 18 mm thick crazy marble stone white, black or as specified — is derived from 16 priced inputs for 100 sqm and works out to ₹1,714.80 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Under layer 25mm thick of cement Concrete
- 1:2:4 =100x0.025=2.5 cum
- Cement slurry for subgrade and under
- large cement
- Top layer with marble pieces and gap
- filling with marble powder mixture Marble
- pieces for crazy flooring (Assume 70%
- of marble stone are and 30% of joint
- filer/mixture 7sqmx0.02m = 0.14 cum
- 10x0.872x0.14/0.051 = 24q
- @ 3.5kg/50kg of cement =
- 10x40.5x3.5/50=28.4kg
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per Item Number 11.7 of SH: FlooringRate as per item 11.7Sub-analysis | cum | 2.5 | 8,595.15 | 21,487.88 | |
| 0367 | Portland CementPortland Cement (OPC-43 Grade)Material | tonne | 0.4 | 5,156.00 | 2,062.40 |
| 0114 | BeldarLabour | day | 5 | 736.00 | 3,680.00 |
| 2710 | White marble makrana second quality plain veined stone pieces for crazy flooringMaterial | quintal | 24 | 164.00 | 3,936.00 |
| 0368 | White CementMaterial | tonne | 0.405 | 10,500.00 | 4,252.50 |
| 0784 | Marble dust/ powderMaterial | cum | 0.07 | 1,180.00 | 82.60 |
| 0875 | Red, chocolate, orange, buff or yellow (red oxide of iron) light shade pigmentRed, chocolate, orange, buff or yellow (red oxide of iron) light shade pigmentMaterial | kilogram | 28.4 | 65.00 | 1,846.00 |
| 0785 | Marble chips upto 4mm and downsize White & blackMarble chips up to 4 mm and down size White & blackMaterial | quintal | 8.72 | 200.00 | 1,744.00 |
| 9977 | Carriage of pigment & marble powderMaterial | L.S. | 36.4 | 2.27 | 82.63 |
| 0123 | Mason 1st classMason 1st classLabour | day | 12 | 897.00 | 10,764.00 |
| 0114 | BeldarLabour | day | 10 | 736.00 | 7,360.00 |
| 0115 | CoolieLabour | day | 10 | 736.00 | 7,360.00 |
| 0139 | Skilled Beldar (for floor rubbing etc.)Labour | day | 50 | 816.00 | 40,800.00 |
| 9999 | Sundries including carborandum etc.Material | L.S. | 1,345.5 | 2.27 | 3,054.29 |
| 0101 | BhistiLabour | day | 5.4 | 816.00 | 4,406.40 |
| 0013 | Machine for rubbing of floorsMachinery | day | 40 | 350.00 | 14,000.00 |
- TOTAL
- 1,26,918.70
- Add 1 % Water charges on “W-A”
- 1,054.31
- TOTAL
- 1,27,973.01
- Add GST on “X-A” (multiplying factor 0.2127)
- 22,649.39
- TOTAL
- 1,50,622.40
- Add 15% CPOH on “Y-A”
- 19,370.18
- TOTAL
- 1,69,992.58
- Add Cess @ 1% on “Z-A”
- 1,485.05
- Cost of 100 Sqm.
- 1,71,477.63
- Cost of 1sqm.
- 1,714.78
- Say
- 1,714.80
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 776. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.