40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under layer 28 mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 12.5 mm nominal size) and top layer 12 mm thick with white, black, chocolate, grey yellow or green marble chips of sizes from 7 mm to 10 mm nominal size, laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 2:3 (2 cement marble powder mix : 3 marble chips) by volume, including cement slurry etc. complete

Dark shade pigment with ordinary cement

Item number
11.11.1
Analysis basis
Details of cost for 100 sqm.
Priced inputs
17
Derived rate
1,110.75 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.11.1 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under layer 28 mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 12.5 mm nominal size) and top layer 12 mm thick with white, black, chocolate, grey yellow or green marble chips of sizes from 7 mm to 10 mm nominal size, laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 2:3 (2 cement marble powder mix : 3 marble chips) by volume, including cement slurry etc. complete Dark shade pigment with ordinary cement — is derived from 17 priced inputs for 100 sqm and works out to ₹1,110.75 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • For under layer 28 mm thick
  • @ 3.5kg/50kg of cement = 10x81x3.5/50=56.7kg
CodeInputUnitQuantityRate (INR)Amount (INR)
0296Stone Aggregate (Single size) : 12.5 mm nominal sizeMaterialcum1.91,400.002,660.00
0297Stone Aggregate (Single size) : 10 mm nominal sizeMaterialcum0.61,400.00840.00
0982Coarse sand (zone III)Materialcum1.251,450.001,812.50
0367Portland Cement (0..0897+0.02)x10Portland Cement (OPC-43 Grade)Materialtonne1.0975,156.005,656.13
0788Marble chips large size above 4 mm White & blackMaterialqtl17.34280.004,855.20
0367Portland CementPortland Cement (OPC-43 Grade)Materialtonne0.815,156.004,176.36
0784Marble dust/ powderMaterialcum0.171,180.00200.60
0874Black colour dark shade pigmentMaterialkg56.775.004,252.50
9977Carriage of pigment and marble powder etcMaterialL.S.62.42.27141.65
0124Mason 2nd classMason 2nd classLabourday17.9816.0014,606.40
0114BeldarLabourday19.9736.0014,646.40
0101BhistiLabourday10.4816.008,486.40
0139Skilled Beldar (for floor rubbing etc.)Labourday10816.008,160.00
0127Driver (for Road Roller, Concrete Mixer, Truck etc.)Driver for (Road roller, concrete mixer, Trucks etc.)Labourday0.3897.00269.10
0002Hire charges of Concrete Mixer 0.25 to 0.40 cum with hooperHire charges of Concrete Mixer 0.25 to 0.40 cum with HopperMachineryday0.3900.00270.00
0013Machine for rubbing of floorsMachineryday10350.003,500.00
9999SundriesMaterialL.S.1,561.32.273,544.15
TOTAL
78,077.39
Add 1 % Water charges on “W”
780.77
TOTAL
78,858.16
Add GST on “X” (multiplying factor 0.2127)
16,773.13
TOTAL
95,631.29
Add 15% CPOH on “Y”
14,344.69
TOTAL
1,09,975.98
Add Cess @ 1% on “Z”
1,099.76
Cost of 100 sqm.
1,11,075.74
Cost of 1 sqm.
1,110.76
Say
1,110.75

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 768. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.