Skip to main content

CPWD Analysis of Rates · Flooring

40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under layer 31 mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 12.5 mm nominal size) and top layer 9 mm thick with white, black, chocolate, grey, yellow or green marble chips of sizes from 4 mm to 7 mm nominal size, laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 4:7 (4 cement marble powder : 7 marble chips) by volume, including cement slurry etc. complete

Ordinary cement without any pigment

Item number
11.10.6
Analysis basis
Details of cost for 100 sqm.
Priced inputs
15
Derived rate
1,027.10 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.10.6 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under layer 31 mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 12.5 mm nominal size) and top layer 9 mm thick with white, black, chocolate, grey, yellow or green marble chips of sizes from 4 mm to 7 mm nominal size, laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 4:7 (4 cement marble powder : 7 marble chips) by volume, including cement slurry etc. complete Ordinary cement without any pigment — is derived from 15 priced inputs for 100 sqm and works out to ₹1,027.10 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • For Under layer of 31 mm thick
CodeInputUnitQuantityRate (INR)Amount (INR)
0296Stone Aggregate (Single size) : 12.5 mm nominal sizeMaterialcum2.11,400.002,940.00
0297Stone Aggregate (Single size) : 10 mm nominal sizeMaterialcum0.71,400.00980.00
0982Coarse sand (zone III)Materialcum1.41,450.002,030.00
0367Portland Cement (0.1005+0.02)Portland Cement (OPC-43 Grade)Materialtonne1.2055,156.006,212.98
0788Marble chips large size above 4 mm White & blackMaterialqtl14280.003,920.00
0367Portland CementPortland Cement (OPC-43 Grade)Materialtonne0.5785,156.002,980.17
0784Marble dust/ powderMaterialcum0.121,180.00141.60
0124Mason 2nd classMason 2nd classLabourday17.9816.0014,606.40
0114BeldarLabourday19.9736.0014,646.40
0101BhistiLabourday10.4816.008,486.40
0139Skilled Beldar (for floor rubbing etc.)Labourday10816.008,160.00
0127Driver (for Road Roller, Concrete Mixer, Truck etc.)Driver for (Road roller, concrete mixer, Trucks etc.)Labourday0.3897.00269.10
0002Hire charges of Concrete Mixer 0.25 to 0.40 cum with hooperHire charges of Concrete Mixer 0.25 to 0.40 cum with HopperMachineryday0.3900.00270.00
0013Machine for rubbing of floorsMachineryday10350.003,500.00
9999SundriesMaterialL.S.1,345.52.273,054.29
TOTAL
72,197.34
Add 1 % Water charges on “W”
721.97
TOTAL
72,919.31
Add GST on “X” (multiplying factor 0.2127)
15,509.94
TOTAL
88,429.25
Add 15% CPOH on “Y”
13,264.39
TOTAL
1,01,693.64
Add Cess @ 1% on “Z”
1,016.94
Cost of 100 sqm
1,02,710.58
Cost of 1 sqm
1,027.11
Say
1,027.10

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 767. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works