Coal tarring two coats on new work using 0.16 Litre and 0.12 litre coal tar per sqm in the first coat and second coat respectively

Item number
13.59
Analysis basis
Detail of cost for 10 sqm
Priced inputs
7
Derived rate
66.90 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.59 Coal tarring two coats on new work using 0.16 Litre and 0.12 litre coal tar per sqm in the first coat and second coat respectively — is derived from 7 priced inputs for 10 sqm and works out to ₹66.90 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
9999LimeMaterialL.S.1.432.273.25
0324Coal TarMateriallitre2.835.0098.00
9977Carriage of materialMaterialL.S.1.432.273.25
0771Kerosene oilMateriallitre0.550.0025.00
0114BeldarLabourday0.43736.00316.48
9999Brushes etcMaterialL.S.5.332.2712.10
9999SundriesMaterialL.S.5.332.2712.10
TOTAL
470.18
Add 1 % Water charges on “W”
4.70
TOTAL
474.88
Add GST on “X” (multiplying factor 0.2127)
101.01
TOTAL
575.89
Add 15% CPOH on “Y”
86.38
TOTAL
662.27
Add Cess @ 1% on “Z”
6.62
Cost of 10.00 sqm
668.89
Cost of 1.00 sqm
66.89
Say
66.90

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 999. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works