Coal tarring two coats on new work using 0.16 Litre and 0.12 litre coal tar per sqm in the first coat and second coat respectively

Item number
13.59
Analysis basis
10 sqm
Priced inputs
7
Derived rate
₹66.90/ SQM
D-01/RATE ANALYSISITEM 13.59

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.59 (Coal tarring two coats on new work using 0.16 Litre and 0.12 litre coal tar per sqm in the first coat and second coat respectively) is derived from 7 priced inputs for 10 sqm and works out to ₹66.90 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 13.59DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
9999MATLimeL.S.1.432.273.25
0324MATCoal Tarlitre2.835.0098.00
9977MATCarriage of materialL.S.1.432.273.25
0771MATKerosene oillitre0.550.0025.00
0114LABBeldarday0.43736.00316.48
9999MATBrushes etcL.S.5.332.2712.10
9999MATSundriesL.S.5.332.2712.10
BUILD-UP TO RATE
TOTAL
470.18
Add 1 % Water charges on “W”
+4.70
TOTAL
474.88
Add GST on “X” (multiplying factor 0.2127)
+101.01
TOTAL
575.89
Add 15% CPOH on “Y”
+86.38
TOTAL
662.27
Add Cess @ 1% on “Z”
+6.62
Cost of 10.00 sqm
668.89
Cost of 1.00 sqm
66.89
SAY
₹66.90
D-02/SOURCEPRINTED PAGE 999
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
999

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 999. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.