Providing and applying two coats of fire retardant paint on cleaned wood / ply surface @ 3.5 sqm per litre per coat including preparation of base surface as per recommendations of manufacturer to make the surface fire retardant
- Item number
- 13.58
- Analysis basis
- 10 sqm
- Priced inputs
- 6
- Derived rate
- ₹334.50/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.58 (Providing and applying two coats of fire retardant paint on cleaned wood / ply surface @ 3.5 sqm per litre per coat including preparation of base surface as per recommendations of manufacturer to make the surface fire retardant) is derived from 6 priced inputs for 10 sqm and works out to ₹334.50 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7240 | MAT | Fire retardant paint | litre | 5.7 | 259.00 | 1,476.30 |
| 9977 | MAT | Carriage of material | L.S. | 1.43 | 2.27 | 3.25 |
| 0131 | LAB | Painter | day | 0.54 | 816.00 | 440.64 |
| 0114 | LAB | Beldar | day | 0.54 | 736.00 | 397.44 |
| 9999 | MAT | Putty, brushes, sand paper etc | L.S. | 6.76 | 2.27 | 15.35 |
| 9999 | MAT | Sundries | L.S. | 8.06 | 2.27 | 18.30 |
- TOTAL
- 2,351.28
- Add 1 % Water charges on “W”
- +23.51
- TOTAL
- 2,374.79
- Add GST on “X” (multiplying factor 0.2127)
- +505.12
- TOTAL
- 2,879.91
- Add 15% CPOH on “Y”
- +431.99
- TOTAL
- 3,311.90
- Add Cess @ 1% on “Z”
- +33.12
- Cost of 10.00 sqm
- 3,345.02
- Cost of 1.00 sqm
- 334.50
- SAY
- ₹334.50
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 998
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 998. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.