Providing and applying two coats of fire retardant paint on cleaned wood / ply surface @ 3.5 sqm per litre per coat including preparation of base surface as per recommendations of manufacturer to make the surface fire retardant

Item number
13.58
Analysis basis
10 sqm
Priced inputs
6
Derived rate
₹334.50/ SQM
D-01/RATE ANALYSISITEM 13.58

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.58 (Providing and applying two coats of fire retardant paint on cleaned wood / ply surface @ 3.5 sqm per litre per coat including preparation of base surface as per recommendations of manufacturer to make the surface fire retardant) is derived from 6 priced inputs for 10 sqm and works out to ₹334.50 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 13.58DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7240MATFire retardant paintlitre5.7259.001,476.30
9977MATCarriage of materialL.S.1.432.273.25
0131LABPainterday0.54816.00440.64
0114LABBeldarday0.54736.00397.44
9999MATPutty, brushes, sand paper etcL.S.6.762.2715.35
9999MATSundriesL.S.8.062.2718.30
BUILD-UP TO RATE
TOTAL
2,351.28
Add 1 % Water charges on “W”
+23.51
TOTAL
2,374.79
Add GST on “X” (multiplying factor 0.2127)
+505.12
TOTAL
2,879.91
Add 15% CPOH on “Y”
+431.99
TOTAL
3,311.90
Add Cess @ 1% on “Z”
+33.12
Cost of 10.00 sqm
3,345.02
Cost of 1.00 sqm
334.50
SAY
₹334.50
D-02/SOURCEPRINTED PAGE 998
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
998

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 998. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.