Pointing on stone slab ceiling with cement mortar 1:2 (1 cement : 2 fine sand)
- Item number
- 13.35.1
- Analysis basis
- 10 sqm
- Priced inputs
- 5
- Derived rate
- ₹214.20/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.35.1 (Pointing on stone slab ceiling with cement mortar 1:2 (1 cement : 2 fine sand): Flush/ Ruled pointing) is derived from 5 priced inputs for 10 sqm and works out to ₹214.20 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Cement mortar 1:2 (1 cement : 2 fine sand)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per Item Number 3.2 of SH: MortarsRate as per item 3.2 | cum | 0.015 | 5,138.00 | 77.07 | |
| 0155 | LAB | Mason (average) | day | 0.47 | 857.00 | 402.79 |
| 0115 | LAB | Coolie | day | 0.69 | 736.00 | 507.84 |
| 0101 | LAB | Bhisti | day | 0.59 | 816.00 | 481.44 |
| 9999 | MAT | Scaffolding and racking out joints including sundries | L.S. | 16.12 | 2.27 | 36.59 |
- TOTAL
- 1,505.73
- Add 1 % Water charges on “W”
- +15.06
- TOTAL
- 1,520.79
- Add GST on “X” (multiplying factor 0.2127)
- +323.47
- TOTAL
- 1,844.26
- Add 15% CPOH on “Y”
- +276.64
- TOTAL
- 2,120.90
- Add Cess @ 1% on “Z”
- +21.21
- Cost of 10.00 sqm
- 2,142.11
- Cost of 1.00 sqm
- 214.21
- SAY
- ₹214.20
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 982
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 982. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate