Pointing on stone slab ceiling with cement mortar 1:2 (1 cement : 2 fine sand)

Flush/ Ruled pointing
Item number
13.35.1
Analysis basis
10 sqm
Priced inputs
5
Derived rate
₹214.20/ SQM
D-01/RATE ANALYSISITEM 13.35.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.35.1 (Pointing on stone slab ceiling with cement mortar 1:2 (1 cement : 2 fine sand): Flush/ Ruled pointing) is derived from 5 priced inputs for 10 sqm and works out to ₹214.20 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement mortar 1:2 (1 cement : 2 fine sand)
ANALYSIS OF RATES · ITEM 13.35.1DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item Number 3.2 of SH: MortarsRate as per item 3.2cum0.0155,138.0077.07
0155LABMason (average)day0.47857.00402.79
0115LABCoolieday0.69736.00507.84
0101LABBhistiday0.59816.00481.44
9999MATScaffolding and racking out joints including sundriesL.S.16.122.2736.59
BUILD-UP TO RATE
TOTAL
1,505.73
Add 1 % Water charges on “W”
+15.06
TOTAL
1,520.79
Add GST on “X” (multiplying factor 0.2127)
+323.47
TOTAL
1,844.26
Add 15% CPOH on “Y”
+276.64
TOTAL
2,120.90
Add Cess @ 1% on “Z”
+21.21
Cost of 10.00 sqm
2,142.11
Cost of 1.00 sqm
214.21
SAY
₹214.20
D-02/SOURCEPRINTED PAGE 982
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
982

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 982. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFINISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.