Raised and cut pointing on stone work in white cement mortar 1:3 (1 white cement : 3 marble dust)

Item number
13.34
Analysis basis
10 sqm
Priced inputs
6
Derived rate
₹716.95/ SQM
D-01/RATE ANALYSISITEM 13.34

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.34 (Raised and cut pointing on stone work in white cement mortar 1:3 (1 white cement : 3 marble dust)) is derived from 6 priced inputs for 10 sqm and works out to ₹716.95 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • White Cement mortar 1:3 (1 white cement :
  • 3 marble dust)
ANALYSIS OF RATES · ITEM 13.34DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item Number 3.16 of SH: MortarsRate as per item 3.16cum0.0387,318.50278.10
9999MATSundriesL.S.7.152.2716.23
0155LABMason (average)day2857.001,714.00
0115LABCoolieday2.96736.002,178.56
0101LABBhistiday1816.00816.00
9999MATScaffolding and racking out joints including sundriesL.S.16.122.2736.59
BUILD-UP TO RATE
TOTAL
5,039.48
Add 1 % Water charges on “W”
+50.39
TOTAL
5,089.87
Add GST on “X” (multiplying factor 0.2127)
+1,082.62
TOTAL
6,172.49
Add 15% CPOH on “Y”
+925.87
TOTAL
7,098.36
Add Cess @ 1% on “Z”
+70.98
Cost of 10.00 sqm
7,169.34
Cost of 1.00 sqm
716.93
SAY
₹716.95
D-02/SOURCEPRINTED PAGE 981
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
981

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 981. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.