Pointing on brick work or brick flooring with cement mortar 1:3 (1 cement : 3 fine sand)

Flush / Ruled/ Struck or weathered pointing
Item number
13.31.1
Analysis basis
10 sqm
Priced inputs
6
Derived rate
₹257.35/ SQM
D-01/RATE ANALYSISITEM 13.31.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.31.1 (Pointing on brick work or brick flooring with cement mortar 1:3 (1 cement : 3 fine sand): Flush / Ruled/ Struck or weathered pointing) is derived from 6 priced inputs for 10 sqm and works out to ₹257.35 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement mortar 1 : 3 (1 cement : 3 fine
  • sand)
ANALYSIS OF RATES · ITEM 13.31.1DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item Number 3.3 of SH: MortarsRate as per item 3.3cum0.034,379.05131.37
0155LABMason (average)day0.5857.00428.50
0115LABCoolieday0.6736.00441.60
0101LABBhistiday0.93816.00758.88
9999MATSundriesL.S.7.152.2716.23
9999MATScaffolding and racking out joints including sundriesL.S.14.32.2732.46
BUILD-UP TO RATE
TOTAL
1,809.04
Add 1 % Water charges on “W”
+18.09
TOTAL
1,827.13
Add GST on “X” (multiplying factor 0.2127)
+388.63
TOTAL
2,215.76
Add 15% CPOH on “Y”
+332.36
TOTAL
2,548.12
Add Cess @ 1% on “Z”
+25.48
Cost of 10.00 sqm
2,573.60
Cost of 1.00 sqm
257.36
SAY
₹257.35
D-02/SOURCEPRINTED PAGE 979
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
979

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 979. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFINISHING