Skip to main content
R/DAR 2023

18 mm thick moulded cement mortar band in two coats under layer 12 mm thick with cement mortar 1:5 (1 cement : 5 coarse sand) top layer 6 mm thick with cement mortar 1:4 (1 cement : 4 fine sand)

Item number
13.30
Analysis basis
10 metre
Priced inputs
6
Derived rate
₹21.45/ METRE LONG AND 1 CM WIDE BAND
D-01/RATE ANALYSISITEM 13.30

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.30 (18 mm thick moulded cement mortar band in two coats under layer 12 mm thick with cement mortar 1:5 (1 cement : 5 coarse sand) top layer 6 mm thick with cement mortar 1:4 (1 cement : 4 fine sand)) is derived from 6 priced inputs for 10 metre and works out to ₹21.45 per metre long and 1 cm wide band after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • wide band
  • Cement mortar 1 : 5 (1 cement : 5 coarse
  • sand)
  • Cement mortar 1 : 4 (1 cement : 4 fine
  • sand)
ANALYSIS OF RATES · ITEM 13.30DETAIL OF COST FOR 10 METRE LONG AND 10 CM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item Number 3.10 of SH: MortarsRate as per item 3.10cum0.0143,850.7553.91
SUBRate as per Item Number 3.4 of SH: MortarsRate as per item 3.4cum0.013,708.8037.09
0155LABMason (average)day0.86857.00737.02
0115LABCoolieday0.86736.00632.96
0101LABBhistiday0.05816.0040.80
9999MATSundriesL.S.2.732.276.20
BUILD-UP TO RATE
TOTAL
1,507.98
Add 1 % Water charges on “W”
+15.08
TOTAL
1,523.06
Add GST on “X” (multiplying factor 0.2127)
+323.95
TOTAL
1,847.01
Add 15% CPOH on “Y”
+277.05
TOTAL
2,124.06
Add Cess @ 1% on “Z”
+21.24
Cost of 10.00 metre long and 10 cm wide band
2,145.30
Cost of 1.00 metre long and 1 cm wide band
21.45
SAY
₹21.45
D-02/SOURCEPRINTED PAGE 978
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
978

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 978. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFINISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.