18 mm thick moulded cement mortar band in two coats under layer 12 mm thick with cement mortar 1:5 (1 cement : 5 coarse sand) top layer 6 mm thick with cement mortar 1:4 (1 cement : 4 fine sand)
- Item number
- 13.30
- Analysis basis
- 10 metre
- Priced inputs
- 6
- Derived rate
- ₹21.45/ METRE LONG AND 1 CM WIDE BAND
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.30 (18 mm thick moulded cement mortar band in two coats under layer 12 mm thick with cement mortar 1:5 (1 cement : 5 coarse sand) top layer 6 mm thick with cement mortar 1:4 (1 cement : 4 fine sand)) is derived from 6 priced inputs for 10 metre and works out to ₹21.45 per metre long and 1 cm wide band after water charges, GST, CPOH and cess. The full build-up is below.
- wide band
- Cement mortar 1 : 5 (1 cement : 5 coarse
- sand)
- Cement mortar 1 : 4 (1 cement : 4 fine
- sand)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per Item Number 3.10 of SH: MortarsRate as per item 3.10 | cum | 0.014 | 3,850.75 | 53.91 | |
| SUB | Rate as per Item Number 3.4 of SH: MortarsRate as per item 3.4 | cum | 0.01 | 3,708.80 | 37.09 | |
| 0155 | LAB | Mason (average) | day | 0.86 | 857.00 | 737.02 |
| 0115 | LAB | Coolie | day | 0.86 | 736.00 | 632.96 |
| 0101 | LAB | Bhisti | day | 0.05 | 816.00 | 40.80 |
| 9999 | MAT | Sundries | L.S. | 2.73 | 2.27 | 6.20 |
- TOTAL
- 1,507.98
- Add 1 % Water charges on “W”
- +15.08
- TOTAL
- 1,523.06
- Add GST on “X” (multiplying factor 0.2127)
- +323.95
- TOTAL
- 1,847.01
- Add 15% CPOH on “Y”
- +277.05
- TOTAL
- 2,124.06
- Add Cess @ 1% on “Z”
- +21.24
- Cost of 10.00 metre long and 10 cm wide band
- 2,145.30
- Cost of 1.00 metre long and 1 cm wide band
- 21.45
- SAY
- ₹21.45
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 978
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 978. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.