CPWD Analysis of Rates · Finishing

18 mm thick moulded cement mortar band in two coats under layer 12 mm thick with cement mortar 1:5 (1 cement : 5 coarse sand) top layer 6 mm thick with cement mortar 1:4 (1 cement : 4 fine sand)

Item number
13.30
Analysis basis
Detail of cost for 10 metre long and 10 cm
Priced inputs
6
Derived rate
21.45 / metre long and 1 cm wide band

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.30 18 mm thick moulded cement mortar band in two coats under layer 12 mm thick with cement mortar 1:5 (1 cement : 5 coarse sand) top layer 6 mm thick with cement mortar 1:4 (1 cement : 4 fine sand) — is derived from 6 priced inputs for 10 metre and works out to ₹21.45 per metre long and 1 cm wide band after water charges, GST, CPOH and cess. The full build-up is below.

  • wide band
  • Cement mortar 1 : 5 (1 cement : 5 coarse
  • sand)
  • Cement mortar 1 : 4 (1 cement : 4 fine
  • sand)
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per Item Number 3.10 of SH: MortarsRate as per item 3.10Sub-analysiscum0.0143,850.7553.91
Rate as per Item Number 3.4 of SH: MortarsRate as per item 3.4Sub-analysiscum0.013,708.8037.09
0155Mason (average)Labourday0.86857.00737.02
0115CoolieLabourday0.86736.00632.96
0101BhistiLabourday0.05816.0040.80
9999SundriesMaterialL.S.2.732.276.20
TOTAL
1,507.98
Add 1 % Water charges on “W”
15.08
TOTAL
1,523.06
Add GST on “X” (multiplying factor 0.2127)
323.95
TOTAL
1,847.01
Add 15% CPOH on “Y”
277.05
TOTAL
2,124.06
Add Cess @ 1% on “Z”
21.24
Cost of 10.00 metre long and 10 cm wide band
2,145.30
Cost of 1.00 metre long and 1 cm wide band
21.45
Say
21.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 978. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works