Skip to main content
R/DAR 2023

12 mm thick plain cement mortar bands in cement mortar 1:4 (1 cement : 4 fine sand)

Raised Band
Item number
13.28.3
Analysis basis
10 metre
Priced inputs
5
Derived rate
₹9.35/ METRE LONG AND 1 CM WIDE BAND
D-01/RATE ANALYSISITEM 13.28.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.28.3 (12 mm thick plain cement mortar bands in cement mortar 1:4 (1 cement : 4 fine sand): Raised Band) is derived from 5 priced inputs for 10 metre and works out to ₹9.35 per metre long and 1 cm wide band after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • wide band
  • Cement mortar 1 : 4 (1 cement : 4 fine
  • sand)
ANALYSIS OF RATES · ITEM 13.28.3DETAIL OF COST FOR 10 METRE LONG AND 10 CM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item Number 3.4 of SH: MortarsRate as per item 3.4cum0.0143,708.8051.92
0155LABMason (average)day0.35857.00299.95
0115LABCoolieday0.35736.00257.60
0101LABBhistiday0.05816.0040.80
9999MATSundriesL.S.2.732.276.20
BUILD-UP TO RATE
TOTAL
656.47
Add 1 % Water charges on “W”
+6.56
TOTAL
663.03
Add GST on “X” (multiplying factor 0.2127)
+141.03
TOTAL
804.06
Add 15% CPOH on “Y”
+120.61
TOTAL
924.67
Add Cess @ 1% on “Z”
+9.25
Cost of 10.00 metre long and 10 cm wide band
933.92
Cost of 1.00 metre long and 1 cm wide band
9.34
SAY
₹9.35
D-02/SOURCEPRINTED PAGE 975
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
975

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 975. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFINISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.