12 mm thick plain cement mortar bands in cement mortar 1:4 (1 cement : 4 fine sand)

Sunk Band
Item number
13.28.2
Analysis basis
10 metre
Priced inputs
5
Derived rate
₹8.20/ METRE LONG AND 1 CM WIDE BAND
D-01/RATE ANALYSISITEM 13.28.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.28.2 (12 mm thick plain cement mortar bands in cement mortar 1:4 (1 cement : 4 fine sand): Sunk Band) is derived from 5 priced inputs for 10 metre and works out to ₹8.20 per metre long and 1 cm wide band after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • wide band
  • Cement mortar 1 : 4 (1 cement : 4 fine
  • sand)
ANALYSIS OF RATES · ITEM 13.28.2DETAIL OF COST FOR 10 METRE LONG AND 10 CM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item Number 3.4 of SH: MortarsRate as per item 3.4cum0.0143,708.8051.92
0155LABMason (average)day0.3857.00257.10
0115LABCoolieday0.3736.00220.80
0101LABBhistiday0.05816.0040.80
9999MATSundriesL.S.2.082.274.72
BUILD-UP TO RATE
TOTAL
575.34
Add 1 % Water charges on “W”
+5.75
TOTAL
581.09
Add GST on “X” (multiplying factor 0.2127)
+123.60
TOTAL
704.69
Add 15% CPOH on “Y”
+105.70
TOTAL
810.39
Add Cess @ 1% on “Z”
+8.10
Cost of 10.00 metre long and 10 cm wide band
818.49
Cost of 1.00 metre long and 1 cm wide band
8.18
SAY
₹8.20
D-02/SOURCEPRINTED PAGE 975
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
975

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 975. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFINISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.