CPWD Analysis of Rates · Finishing

6 mm cement plaster 1:3 (1 cement : 3 fine sand) finished with a floating coat of neat cement and thick coat of Lime wash on top of walls when dry for bearing of R.C.C. slabs and beams

Item number
13.17
Analysis basis
Detail of cost for 10 sqm
Priced inputs
16
Derived rate
396.65 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.17 6 mm cement plaster 1:3 (1 cement : 3 fine sand) finished with a floating coat of neat cement and thick coat of Lime wash on top of walls when dry for bearing of R.C.C. slabs and beams — is derived from 16 priced inputs for 10 sqm and works out to ₹396.65 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Cement mortar 1 : 3 (1 cement : 3 fine
  • sand)
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per Item Number 3.3 of SH: MortarsRate as per item 3.3Sub-analysiscum0.0724,379.05315.29
0155Mason (average)Labourday0.51857.00437.07
0115CoolieLabourday0.75736.00552.00
0101BhistiLabourday0.92816.00750.72
9999Extra for removing burrs, cleaning with wire brushes, pock making with pointed tool etc. completeMaterialL.S.13.392.2730.40
9999Scaffolding and sundriesMaterialL.S.11.72.2726.56
0367Portland Cement (OPC-43 grade)Materialtonne0.025,156.00103.12
0155Mason (average)Labourday0.27857.00231.39
0115CoolieLabourday0.27736.00198.72
9999Scaffolding and sundriesMaterialL.S.8.062.2718.30
0776Satna limeMaterialquintal0.01400.004.00
9999Indigo gum etcMaterialL.S.2.082.274.72
9999Sundries ladder etc.MaterialL.S.0.522.271.18
0141White WasherLabourday0.07816.0057.12
0115CoolieLabourday0.07736.0051.52
9999SundriesMaterialL.S.2.732.276.20
TOTAL
2,788.31
Add 1 % Water charges on “W”
27.88
TOTAL
2,816.19
Add GST on “X” (multiplying factor 0.2127)
599.00
TOTAL
3,415.19
Add 15% CPOH on “Y”
512.28
TOTAL
3,927.47
Add Cess @ 1% on “Z”
39.27
Cost of 10.00 sqm
3,966.74
Cost of 1.00 sqm
396.67
Say
396.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 966. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.