6 mm cement plaster of mix
- Item number
- 13.16.1
- Analysis basis
- 10 sqm
- Priced inputs
- 6
- Derived rate
- ₹300.45/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.16.1 (6 mm cement plaster of mix : 1:3 (1 cement : 3 fine sand)) is derived from 6 priced inputs for 10 sqm and works out to ₹300.45 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Cement mortar 1 : 3 (1 cement : 3 fine
- sand)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per Item Number 3.3 of SH: MortarsRate as per item 3.3 | cum | 0.072 | 4,379.05 | 315.29 | |
| 0155 | LAB | Mason (average) | day | 0.51 | 857.00 | 437.07 |
| 0115 | LAB | Coolie | day | 0.75 | 736.00 | 552.00 |
| 0101 | LAB | Bhisti | day | 0.92 | 816.00 | 750.72 |
| 9999 | MAT | Extra for removing burrs, cleaning with wire brushes, pock making with pointed tool etc. complete | L.S. | 13.39 | 2.27 | 30.40 |
| 9999 | MAT | Scaffolding and sundries | L.S. | 11.7 | 2.27 | 26.56 |
- TOTAL
- 2,112.04
- Add 1 % Water charges on “W”
- +21.12
- TOTAL
- 2,133.16
- Add GST on “X” (multiplying factor 0.2127)
- +453.72
- TOTAL
- 2,586.88
- Add 15% CPOH on “Y”
- +388.03
- TOTAL
- 2,974.91
- Add Cess @ 1% on “Z”
- +29.75
- Cost of 10.00 sqm
- 3,004.66
- Cost of 1.00 sqm
- 300.47
- SAY
- ₹300.45
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 965
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 965. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.