Varnishing with varnish of approved brand and manufacture
- Item number
- 13.113.2
- Analysis basis
- 10 sqm
- Priced inputs
- 7
- Derived rate
- ₹95.05/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.113.2 (Varnishing with varnish of approved brand and manufacture: One or more coats with spar varnish) is derived from 7 priced inputs for 10 sqm and works out to ₹95.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0858 | MAT | Superior spar varnish | litre | 0.75 | 115.00 | 86.25 |
| 9977 | MAT | Carriage | L.S. | 0.52 | 2.27 | 1.18 |
| 9999 | MAT | Repair etc | L.S. | 2.73 | 2.27 | 6.20 |
| 0131 | LAB | Painter | day | 0.36 | 816.00 | 293.76 |
| 0115 | LAB | Coolie | day | 0.36 | 736.00 | 264.96 |
| 9999 | MAT | Brushes, sand paper etc | L.S. | 2.73 | 2.27 | 6.20 |
| 9999 | MAT | Sundries | L.S. | 4.16 | 2.27 | 9.44 |
- TOTAL
- 667.99
- Add 1 % Water charges on “W”
- +6.68
- TOTAL
- 674.67
- Add GST on “X” (multiplying factor 0.2127)
- +143.50
- TOTAL
- 818.17
- Add 15% CPOH on “Y”
- +122.73
- TOTAL
- 940.90
- Add Cess @ 1% on “Z”
- +9.41
- Cost of 10.00 sqm
- 950.31
- Cost of 1.00 sqm
- 95.03
- SAY
- ₹95.05
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1032
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1032. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.