Excavation work by mechanical means (Hydraulic excavator)/ manual means in foundation trenches or drains (not exceeding 1.5m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soils as directed, within a lead of 50 m
- Item number
- 2.9.3
- Analysis basis
- 10 cum
- Priced inputs
- 9
- Derived rate
- ₹1,523.05/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.9.3 (Excavation work by mechanical means (Hydraulic excavator)/ manual means in foundation trenches or drains (not exceeding 1.5m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soils as directed, within a lead of 50 m Hard rock (blasting prohibited)) is derived from 9 priced inputs for 10 cum and works out to ₹1,523.05 per cum after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0020 | MACH | Hydraulic Excavator (3D) with driver and fuel.Hydraulic Excavator (3D) with driver and fuel | day | 0.125 | 7,850.00 | 981.25 |
| 0017 | MACH | Hire and running charges of tipper | day | 0.125 | 4,200.00 | 525.00 |
| 0132 | LAB | Rock Excavator | day | 2.65 | 736.00 | 1,950.40 |
| 0133 | LAB | Rock Breaker | day | 6.175 | 736.00 | 4,544.80 |
| 0135 | LAB | Stone Chiseller | day | 1.06 | 816.00 | 864.96 |
| 0103 | LAB | Blacksmith 2nd class | day | 0.175 | 816.00 | 142.80 |
| 0114 | LAB | Beldar | day | 0.75 | 736.00 | 552.00 |
| 0115 | LAB | Coolie | day | 1.5 | 736.00 | 1,104.00 |
| 9999 | MAT | Sundries | L.S. | 17.94 | 2.27 | 40.72 |
- TOTAL
- 10,705.93
- Add 1 % Water charges on “W”
- +107.06
- TOTAL
- 10,812.99
- Add GST on “X” (multiplying factor 0.2127)
- +2,299.92
- TOTAL
- 13,112.91
- Add 15% CPOH on “Y”
- +1,966.94
- TOTAL
- 15,079.85
- Add Cess @ 1% on “Z”
- +150.80
- Cost of 10 cum.
- 15,230.65
- Cost of 1 cum.
- 1,523.07
- SAY
- ₹1,523.05
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 99
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 99. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.