Excavating trenches by mechinical / manual means of required width for pipes, cables, etc including excavation for sockets, and dressing of sides, ramming of bottoms, for all depth, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20 cm in depth, including consolidating each deposited layer by ramming, watering, etc. and disposing of surplus excavated soil as directed, within a lead of 50 m : All kinds of soil

Pipes, cables etc, not exceeding 80 mm dia
Item number
2.10.1.1
Analysis basis
180m length
Priced inputs
2
Derived rate
₹215.60/ M LENGTH
D-01/RATE ANALYSISITEM 2.10.1.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.10.1.1 (Excavating trenches by mechinical / manual means of required width for pipes, cables, etc including excavation for sockets, and dressing of sides, ramming of bottoms, for all depth, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20 cm in depth, including consolidating each deposited layer by ramming, watering, etc. and disposing of surplus excavated soil as directed, within a lead of 50 m : All kinds of soil Pipes, cables etc, not exceeding 80 mm dia) is derived from 2 priced inputs for 180m length and works out to ₹215.60 per m length after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • an average dia. say 40mm. Slope assumed
  • 1 in 200.
  • Earth work and fillingMinimum depth of trench 60cm. Average
  • depth = (0.6+1.5)/2 = 1.05, Width for this
  • depth 0.45 cm, 180x0.45x1.05 = 85.05 cum
ANALYSIS OF RATES · ITEM 2.10.1.1DETAILS OF COST FOR 180M LENGTH OF A PIPE OF
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item No. 2.8.1 of SH: Earth workRate as per item 2.8.1cum85.05260.3022,138.52
SUBRate as per Item No. 2.25 of SH: Earth WorkRate as per item 2.25cum85.05196.0016,669.80
BUILD-UP TO RATE
TOTAL
38,808.32
Cost of 180m length of pipes
38,808.32
Cost for 1m. length of pipe
215.60
SAY
₹215.60
D-02/SOURCEPRINTED PAGE 99
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
99

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 99. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSEARTH WORK