CPWD Analysis of Rates · Earth Work
Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge
Hard rock (blasting prohibited)
- Item number
- 2.7.3
- Analysis basis
- Details of cost for 10 cum.
- Priced inputs
- 9
- Derived rate
- ₹1,432.95 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.7.3 — Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge Hard rock (blasting prohibited) — is derived from 9 priced inputs for 10 cum and works out to ₹1,432.95 per cum after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0020 | Hydraulic Excavator (3D) with driver and fuel.Hydraulic Excavator (3D) with driver and fuelMachinery | day | 0.125 | 7,850.00 | 981.25 |
| 0017 | Hire and running charges of tipperMachinery | day | 0.125 | 4,200.00 | 525.00 |
| 0132 | Rock ExcavatorLabour | day | 2.47 | 736.00 | 1,817.92 |
| 0133 | Rock BreakerLabour | day | 6 | 736.00 | 4,416.00 |
| 0135 | Stone ChisellerLabour | day | 1.06 | 816.00 | 864.96 |
| 0103 | Blacksmith 2nd classLabour | day | 0.175 | 816.00 | 142.80 |
| 0114 | BeldarLabour | day | 0.75 | 736.00 | 552.00 |
| 0115 | CoolieLabour | day | 1 | 736.00 | 736.00 |
| 9999 | SundriesMaterial | L.S. | 16.12 | 2.27 | 36.59 |
- TOTAL
- 10,072.52
- Add 1 % Water charges on “W”
- 100.73
- TOTAL
- 10,173.25
- Add GST on “X” (multiplying factor 0.2127)
- 2,163.85
- TOTAL
- 12,337.10
- Add 15% CPOH on “Y”
- 1,850.57
- TOTAL
- 14,187.67
- Add Cess @ 1% on “Z”
- 141.88
- Cost of 10 cum.
- 14,329.55
- Cost of 1 cum.
- 1,432.96
- Say
- 1,432.95
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 97. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.