CPWD Analysis of Rates · Earth Work

Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge

Hard rock (requiring blasting)

Item number
2.7.2
Analysis basis
Details of cost for 10 cum.
Priced inputs
10
Derived rate
874.40 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.7.2 Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge Hard rock (requiring blasting) — is derived from 10 priced inputs for 10 cum and works out to ₹874.40 per cum after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0020Hydraulic Excavator (3D) with driver and fuel.Hydraulic Excavator (3D) with driver and fuelMachineryday0.1257,850.00981.25
0017Hire and running charges of tipperMachineryday0.1254,200.00525.00
0132Rock ExcavatorLabourday1.06736.00780.16
0133Rock BreakerLabourday2.825736.002,079.20
0134Rock Hole DrillerLabourday0.885736.00651.36
0114BeldarLabourday0.45736.00331.20
0115CoolieLabourday0.55736.00404.80
0325Blasting powderMaterialkilogram3.9344.00172.92
0326Blasting fuse (fuse wire)Materialeach446.00184.00
9999SundriesMaterialL.S.16.122.2736.59
TOTAL
6,146.48
Add 1 % Water charges on “W”
61.46
TOTAL
6,207.94
Add GST on “X” (multiplying factor 0.2127)
1,320.43
TOTAL
7,528.37
Add 15% CPOH on “Y”
1,129.26
TOTAL
8,657.63
Add Cess @ 1% on “Z”
86.58
Cost of 10 cum.
8,744.21
Cost of 1 cum.
874.42
Say
874.40

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 96. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works