Skip to main content
R/DAR 2023

Excavating holes more than 0.10 cum & upto 0.5 cum including getting out the excavated soil, then returning the soil as required in layers not exceeding 20cm in depth, including consolidating each deposited layer by ramming, watering etc, disposing of surplus excavated soil, as directed within a lead of 50 m and lift upto 1.5 m

All kinds of soil
Item number
2.30.1
Analysis basis
10 holes
Priced inputs
2
Derived rate
₹82.45/ HOLE
D-01/RATE ANALYSISITEM 2.30.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.30.1 (Excavating holes more than 0.10 cum & upto 0.5 cum including getting out the excavated soil, then returning the soil as required in layers not exceeding 20cm in depth, including consolidating each deposited layer by ramming, watering etc, disposing of surplus excavated soil, as directed within a lead of 50 m and lift upto 1.5 m All kinds of soil) is derived from 2 priced inputs for 10 holes and works out to ₹82.45 per hole after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Earth work 10 x 0.30 (avg) = 3.0 cum
  • Extra labour for filling and ramming
ANALYSIS OF RATES · ITEM 2.30.1DETAILS OF COST FOR 10 HOLES-
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no. 2.8.1 of SH: Earth workRate as per item 2.8.1cum3260.30780.90
9999MATSundriesL.S.13.522.2730.69
BUILD-UP TO RATE
TOTAL
811.59
Add 1 % Water charges on “W-A”
+0.31
TOTAL
811.90
Add GST on “X-A” (multiplying factor 0.2127)
+6.59
TOTAL
818.49
Add 15% CPOH on “Y-A”
+5.64
TOTAL
824.13
Add Cess @ 1% on “Z-A”
+0.43
Cost of 10 holes
824.56
Cost of 1 hole
82.46
SAY
₹82.45
D-02/SOURCEPRINTED PAGE 130
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
130

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 130. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSEARTH WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.