CPWD Analysis of Rates · Earth Work

Excavating holes more than 0.10 cum & upto 0.5 cum including getting out the excavated soil, then returning the soil as required in layers not exceeding 20cm in depth, including consolidating each deposited layer by ramming, watering etc, disposing of surplus excavated soil, as directed within a lead of 50 m and lift upto 1.5 m

All kinds of soil

Item number
2.30.1
Analysis basis
Details of cost for 10 holes-
Priced inputs
2
Derived rate
82.45 / hole

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.30.1 Excavating holes more than 0.10 cum & upto 0.5 cum including getting out the excavated soil, then returning the soil as required in layers not exceeding 20cm in depth, including consolidating each deposited layer by ramming, watering etc, disposing of surplus excavated soil, as directed within a lead of 50 m and lift upto 1.5 m All kinds of soil — is derived from 2 priced inputs for 10 holes and works out to ₹82.45 per hole after water charges, GST, CPOH and cess. The full build-up is below.

  • Earth work 10 x 0.30 (avg) = 3.0 cum
  • Extra labour for filling and ramming
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per item no. 2.8.1 of SH: Earth workRate as per item 2.8.1Sub-analysiscum3260.30780.90
9999SundriesMaterialL.S.13.522.2730.69
TOTAL
811.59
Add 1 % Water charges on “W-A”
0.31
TOTAL
811.90
Add GST on “X-A” (multiplying factor 0.2127)
6.59
TOTAL
818.49
Add 15% CPOH on “Y-A”
5.64
TOTAL
824.13
Add Cess @ 1% on “Z-A”
0.43
Cost of 10 holes
824.56
Cost of 1 hole
82.46
Say
82.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 130. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.