CPWD Analysis of Rates · Earth Work

Extra rates for quantities of works, executed

In or under water and/or liquid mud, including pumping out water as required

Item number
2.24.1
Priced inputs
0

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.24.1 Extra rates for quantities of works, executed: In or under water and/or liquid mud, including pumping out water as required — is derived from 0 priced inputs. The full build-up is below.

  • Extra due to slow progress and dewatering:
  • 20% of the rate of the item
CodeInputUnitQuantityRate (INR)Amount (INR)
Cost of 1 metre depth
NaN
Say
NaN

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 126. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.