Open timbering over areas including strutting, shoring etc. complete. (Measurements to be taken of the face area timbered)

Depth exceeding 3 m but not exceeding 4.5 m
Item number
2.22.3
Analysis basis
10 area
Priced inputs
5
Derived rate
₹71.30/ AREA
D-01/RATE ANALYSISITEM 2.22.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.22.3 (Open timbering over areas including strutting, shoring etc. complete. (Measurements to be taken of the face area timbered): Depth exceeding 3 m but not exceeding 4.5 m) is derived from 5 priced inputs for 10 area and works out to ₹71.30 per area after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 1.5m deep
  • area = 10x30 x 1.50 = 450 sqm.
  • The Material can be used four times on the
  • same work and after use of material credit is
  • given @ 75% of cost
  • Polling boards of
  • 250mm x 38mm
  • 10x40x1.50x0.25x0.038 = 5.7cum. = 5700 dm
  • Qty taken for cost of using once after
  • deducting for credit = 5700x x = 356.25 dm ³
  • Raking struts10x40x1.50 = 600m
  • Qty taken for cost of using once after
  • deducting for credit = 600x x = 37.5 m
ANALYSIS OF RATES · ITEM 2.22.3DETAILS OF COST FOR 10 AREA 30M LONG AND
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1198MATSecond class kail wood in planks10 cudm35.625260.009,262.50
0302MATSafeda ballies 125 mm diameter ¼ ¼ ³Safeda ballies 125 mm diametermetre37.544.001,650.00
0112LABCarpenter 2nd classday5816.004,080.00
0114LABBeldar ¼ ¼Beldarday8.8736.006,476.80
9999MATSundriesL.S.475.82.271,080.07
BUILD-UP TO RATE
TOTAL
22,549.37
Add 1 % Water charges on “W”
+225.49
TOTAL
22,774.86
Add GST on “X” (multiplying factor 0.2127)
+4,844.21
TOTAL
27,619.07
Add 15% CPOH on “Y”
+4,142.86
TOTAL
31,761.93
Add Cess @ 1% on “Z”
+317.62
Cost of 450 sqm.
32,079.55
Cost per sqm.
71.29
SAY
₹71.30
D-02/SOURCEPRINTED PAGE 125
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
125

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 125. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSEARTH WORK