Skip to main content

CPWD Analysis of Rates · Earth Work

Open timbering in case of shafts, wells, cesspits, manholes and the like including strutting and shoring complete (Measurements to be taken of the face area timbered)

Depth exceeding 3 m but not exceeding 4.5 m

Item number
2.21.3
Analysis basis
Details of cost for 10 manholes 1.2x 1m
Priced inputs
6
Derived rate
101.85 / manholes

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.21.3 Open timbering in case of shafts, wells, cesspits, manholes and the like including strutting and shoring complete (Measurements to be taken of the face area timbered): Depth exceeding 3 m but not exceeding 4.5 m — is derived from 6 priced inputs for 10 manholes and works out to ₹101.85 per manholes after water charges, GST, CPOH and cess. The full build-up is below.

  • x1.5m
  • Surface area 10x2(1.20+1.00)x1.50 = 66
  • sqm
  • The Material can be used four times on the
  • same work and after use of material credit is
  • given @ 75% of cost
  • Polling boards of
  • 250mm wide and 38mm thick :
  • 10x6x0.25x1.50x0.038 = 0.86 cum =
  • 860cudm
  • Qty taken for cost of using once after
  • deducting for credit = 860x x = 53.75 dm
  • Walling 100mmxl00mm of
  • 10x4x1.2x0.10x0.10 = 0.48 cum = 480 dm
  • Qty taken for cost of using once after
  • deducting for credit = 480x x = 30 dm ³
  • Struts of
  • [(4x1.0)+(2x1.2)]x10 = 64m
  • Qty taken for cost of using once after
  • deducting for credit = 64x x = 4 m
CodeInputUnitQuantityRate (INR)Amount (INR)
1198Second class kail wood in planksMaterial10 cudm5.375260.001,397.50
1197Second class kail wood in scantling ¼ ¼ ³Second class kail wood in scantlingMaterial10 cudm3260.00780.00
0302Safeda ballies 125 mm diameter ¼ ¼ ³Safeda ballies 125 mm diameterMaterialmetre444.00176.00
0112Carpenter 2nd classLabourday1816.00816.00
0114Beldar ¼ ¼BeldarLabourday2736.001,472.00
9999SundriesMaterialL.S.36.42.2782.63
TOTAL
4,724.13
Add 1 % Water charges on “W”
47.24
TOTAL
4,771.37
Add GST on “X” (multiplying factor 0.2127)
1,014.87
TOTAL
5,786.24
Add 15% CPOH on “Y”
867.94
TOTAL
6,654.18
Add Cess @ 1% on “Z”
66.54
Cost of 66 sqm.
6,720.72
Cost per sqm.
101.83
Say
101.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 122. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works