CPWD Analysis of Rates · Earth Work
Open timbering in trenches including strutting and shoring complete (measurements to be taken of the face area timbered)
Depth exceeding 3 m but not exceeding 4.5 m
- Item number
- 2.20.3
- Analysis basis
- Details of cost for a trench of length 30m and
- Priced inputs
- 6
- Derived rate
- ₹97.25 / a trench
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.20.3 — Open timbering in trenches including strutting and shoring complete (measurements to be taken of the face area timbered): Depth exceeding 3 m but not exceeding 4.5 m — is derived from 6 priced inputs for a trench and works out to ₹97.25 per a trench after water charges, GST, CPOH and cess. The full build-up is below.
- 1.5m deep
- surface area - 2x30x1.5 = 90 sqm.
- The Material can be used four times on the
- same work and after use of material credit is
- given @ 75% of cost
- Poling boards of
- 1.50mx0.25x0.038m :
- 2x40x1.5x0.25x0.038= 1.14 cum =1140
- cudm
- Qty taken for cost of using once after
- deducting for credit = 1140x x = 71.25
- dm
- Wallings of ¼ ¼
- l00mmxl00mm : 4x30mx0.lmx0.lm =
- 1.20cum= 1200 cudm
- Qty taken for cost of using once after
- deducting for credit = 1200x x = 75 dm
- Struts of
- and 1.5m long
- 2x17x1.5 = 51m
- Qty taken for cost of using once after
- deducting for credit = 51x x = 3.18 m
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1198 | Second class kail wood in planksMaterial | 10 cudm | 7.125 | 260.00 | 1,852.50 |
| 1197 | Second ³ class kail wood in scantlingSecond class kail wood in scantlingMaterial | 10 cudm | 7.5 | 260.00 | 1,950.00 |
| 0302 | Safeda ballies 125 mm diameter ¼ ¼ ³Safeda ballies 125 mm diameterMaterial | metre | 3.18 | 44.00 | 139.92 |
| 0112 | Carpenter 2nd classLabour | day | 1 | 816.00 | 816.00 |
| 0114 | Beldar ¼ ¼BeldarLabour | day | 1.75 | 736.00 | 1,288.00 |
| 9999 | SundriesMaterial | L.S. | 46.67 | 2.27 | 105.94 |
- TOTAL
- 6,152.36
- Add 1 % Water charges on “W”
- 61.52
- TOTAL
- 6,213.88
- Add GST on “X” (multiplying factor 0.2127)
- 1,321.69
- TOTAL
- 7,535.57
- Add 15% CPOH on “Y”
- 1,130.34
- TOTAL
- 8,665.91
- Add Cess @ 1% on “Z”
- 86.66
- Cost of 90 Sqm
- 8,752.57
- Cost per sqm.
- 97.25
- Say
- 97.25
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 120. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.